Loke: LRT3 main contractor liable for RM474.8mil in late penalties


KUALA LUMPUR: The main contractor for the LRT3 project is liable to pay Liquidated and Ascertained Damages (LAD) amounting to RM474.8mil as of Dec 31 last year.

Transport Minister Anthony Loke said the figure was calculated based on the stipulated daily LAD rate of RM2.7mil imposed on the contractor for each day of delay.

He explained that, calculated from the expiry of Extension of Time No. 2 on July 10, 2025, the total delay up to Dec 31, 2025, stood at 174 days.

"The main contractor is fully aware of the LAD, and Prasarana Malaysia Berhad has obtained assurances from the contractor that all outstanding issues will be addressed and resolved in the near term," he said during question time in the Dewan Rakyat on Tuesday (March 3).

Loke was responding to Syahredzan Johan (PH-Bangi), who asked about the total LAD to be imposed on Setia Utama LRT3 Sdn Bhd as of Dec 31, 2025, for failing to meet the LRT3 project completion schedule, and whether the delay involved Siemens' failure to deliver satisfactory software on time.

He said that, in addition to the signalling system supplier Siemens failing to deliver satisfactory software within the stipulated timeline, several other factors also contributed to the project's delay.

These include delays in carrying out critical testing for other system packages, such as the communications system, as well as the System Integration Test (SIT), which has since been completed.

There were also several failures recorded during the Fault Free Run (FFR) trials.

Loke said Prasarana Malaysia Berhad is currently focused on completing the remaining FFR testing involving eight train sets. – Bernama

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Come back to vote, DAP candidate urges Johoreans
Sweet tooth stick up: Premium-grade durian carted away by machete-wielding robbers from Jasin orchard
Woman reported missing in Taiping safe, denies kidnapping claims
Appointment of 22nd Undang of Rembau done without palace interference, says customary council
Seven police reports received over cemetery burial dispute, says cops
Fama to implement plan to help reduce impact of durian oversupply in Penang
Johor polls: MCA firmly committed to BN's solo electoral strategy, says Dr Wee
Finance Ministry allocates RM5.5mil for Langkawi sea ambulance service
Two nabbed after KL police chase remanded for five days
State govt seeking permanent solution to Rohingya issue through repatriation, says Melaka CM

Others Also Read