Audit: Phase 1 of Langat 2 water project yet to meet implementation objective


KUALA LUMPUR (Bernama): The implementation of Phase 1 of the Langat 2 Water Treatment Plant and Distribution System (LRAL2) project has yet to meet its objective to supply 1,130 million litres of treated water per day to areas around Selangor and Kuala Lumpur.

According to the Auditor-General’s Report 2019 Series 2 released on Tuesday (Sept 28), the performance of the project was unsatisfactory as the delay in completing the water distribution system work package had hampered the distribution of treated water to the northern and western corridors.

At the same time, the management of the project was inefficient because there were significant weaknesses at the project planning stage involving the delay in finalising the Restructuring of the Water Services Industry for Selangor.

In addition, the report said that the land acquisition and alienation to the Federal Land Commissioner had not been completed and the expenditure made for Phase 1 was RM2,853,70mil, exceeding the estimated allocation approved by the Cabinet (RM2,103mil).

"The full operation of treated water pumps, generators, transformers and the Scada (Supervisory control and data acquisition) system according to specification also cannot be ensured as the complete components of the LRAL2 project have not been integrated,” the report said.

The Auditor-General's Report recommended that the Environment and Water Ministry monitor the completion of the construction work of the water distribution system according to the set time period as an improvement action.

Apart from that, Pengurusan Aset Air Bhd and the Ministry also needed to expedite the land acquisition process and land alienation application to the Federal Land Commissioner, and take immediate action on all pending testing and commissioning works.

Meanwhile, the Pahang-Selangor Raw Water Transfer Project, which is among the solutions for the clean water supply issue in Selangor, Kuala Lumpur and Putrajaya until 2025, has yet to meet the target of distributing 1,890 million litres of water per day, due to the delay in the LRAL2 project.

According to the Auditor-General's Report, the delay had caused the capacity of raw water distribution from Pahang to Selangor to only achieve 623 million litres per day for six months until 2020.

"Overall, the implementation of the raw water transfer project is satisfactory, however coordination at the ministry, Pahang and Selangor state governments, as well as relevant departments and agencies has to be increased,” the report said.

Besides that, issues involving financial management, ownership and reservation, quantity and quality of raw water, maintenance and encroachment of dam areas needed thorough planning and action because the problems have not been resolved although the project has been completed.

Therefore, the report recommended that the Ministry take improvement measures in the management of future projects, such as ensuring the ownership and reservation of land are finalised before the completion of the project, to ensure the transfer of asset ownership of infrastructure projects to receiving agencies is not affected. - Bernama

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Senior citizen found dead after alleged assault, three relatives arrested
Cops cripple love scam, non-existent crypto exchange syndicate, 13 foreigners arrested
Melaka polls: Barisan machinery urged to exercise restraint during campaigning, says Zahid
Malaysia to highlight Gaza crisis at TRT World Forum, says Zahid
MCMC testing internet coverage along ECRL route ahead of Dec 12 launch
Education Ministry to maintain 12 weekly language teaching periods under KP2027
Bukit Aman welcomes proposed cybercrime bill to tackle borderless scams
Heavy rain triggers flash floods in parts of Puncak Alam
S'gor MACC nabs local authority officer for allegedly misappropriating RM60,000
Melaka polls: I’m not here to make new promises, says Anwar

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read