Court: No power to grant extension


Take them to task: According to the liquidated damages clause, condo buyers can claim 10 per annum of the purchase price for the delay.

KUALA LUMPUR: The Housing Controller has no power to grant an extension of time to developers who delay the completion of housing projects, the High Court has ruled in a landmark judgment.

This means a housing developer has to pay compensation to the affected buyers for delays in the delivery of vacant possession.

Win a prize this Mother's Day by subscribing to our annual plan now! T&C applies.

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

News , bureaus

   

Next In Nation

Family of fallen Malaysian peacekeeper finds peace in her honourable service
Cops seize 65 motorcycles, issue 342 summons during enforcement op in Penang
No to violence: Police release photofit of Faisal Halim acid attack suspect
Revoking S'pore comedian's work permit a bad precedent, says PJ MP
Ulu Tiram Attack: Johor religious department steps up monitoring of deviant teaching
Six arrested for street racing in Iskandar Puteri
State leaders question need for two village development committees in Sabah
RM1.2mil subsidised diesel smuggled through Bukit Kayu Hitam daily, says JPJ
Ex-Sabah CM claims confidence in state AGC low, calls for revamp
PAS questions why 'Pinkfish Express' event allowed on chartered train

Others Also Read