Court: No power to grant extension


Take them to task: According to the liquidated damages clause, condo buyers can claim 10 per annum of the purchase price for the delay.

KUALA LUMPUR: The Housing Controller has no power to grant an extension of time to developers who delay the completion of housing projects, the High Court has ruled in a landmark judgment.

This means a housing developer has to pay compensation to the affected buyers for delays in the delivery of vacant possession.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
News , bureaus

Next In Nation

Puad is welcome to join PAS, says Ahmad Samsuri
Johor polls: MIPP to contest five seats under Perikatan
Johor polls: Tangible improvements in Yong Peng prove it's not neglected, says Dr Wee
Johor polls: Ex-Bersatu's Mazlan Bujang among 11 PAS candidates
Johor polls: Bersatu announces candidates to contest 16 seats
Woman held after a motorcyclist killed in three-vehicle crash on SPE Highway
Johor polls: Almost RM53mil poured into Yong Peng over past four years, says incumbent rep Ling Tian Soon
Man dies after jumping off flyover while fleeing cops
Babysitter detained after 11-month-old baby dies
Six arrested in perfume investment scam raid

Others Also Read