KLIA aerotrain back on track


Independent assessors confirm system’s safety despite disruptions

SEPANG: Independent railway assessors have confirmed that the KL International Airport (KLIA) aerotrain system is operating as intended, with service disruptions observed since commissioning being those commonly encountered during the early operational phase of complex rail systems.

In a statement yesterday, Malaysia Airports Holdings Bhd (MAHB) said the assessors found that the disruptions do not pose a safety risk, as structured engineering controls and continuous monitoring are in place to manage the issues effectively.

“During the implementation of the Comprehensive Action Plan (CAP), which commenced on Nov 15 last year, aerotrain operations have remained stable, recording an Operational Service Availability of 100% in December 2025, up from 98.67% in July 2025, reflecting high system availability while inspection, testing and validation activities were carried out,” it said in a report carried by Bernama.

The unnamed independent assessment identified two critical systems with a direct influence on train reliability, service availability and recovery performance, namely the power supply system and the rolling stock.

As for the power supply system, while the overall design and protection systems were found to be adequate and generally operating as intended, areas such as installation quality, power rail condition monitoring and clarity of operational roles were identified for continued focus to strengthen long-term reliability.

For the rolling stock, particular attention was placed on the current collector device, which influences traction continuity and service stability due to its close interaction with the power rail.

According to MAHB, the CAP has been implemented through coordinated work streams covering inspection and rectification, system testing and validation, and trial operations.

“Inspection and rectification activities across the aerotrain system have been completed, with the programme now at the final milestone to close out remaining rectification actions identified during system-wide inspections,” it added.

During the CAP period, MAHB said engineering hours were initially scheduled from 9pm to 7am but were later shortened to 11pm to 7am to accommodate festive and school holiday peaks.

MAHB said it will continue to implement the remaining CAP measures in a coordinated and proportionate manner, supported by ongoing monitoring and independent oversight to further strengthen system reliability and ensure consistent aerotrain operations.

The statement did not say when round-the-clock aerotrain services at KLIA will resume.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
MAHB , aerotrain , KLIA , CAP

Next In Nation

Fourth Malaysian ship transits Strait of Hormuz
Teachers shape the nation's future generation, says Zahid
Former driver charged with criminally intimidating KL High Court judge
Father's love inspires teacher to develop special needs methods
54 GSF ships in Yellow Zone 2, about 340 nautical miles from Gaza coast
CAP urges govt to relist nicotine into Poison Act
Perak police chief vows to tighten monitoring of lockups in state
Gang members charged in Kuching under heavy guard
Lahad Datu and Tawau cut off after 50m stretch of road collapses
Johorean shocked to find his vehicle transferred to KL dealership without consent

Others Also Read