ECRL to mitigate projects impact on wildlife


Fits like a puzzle: ECRL’s Kuantan Bridge was successfully constructed across Jalan Kuantan-Sungai Lembing.

KUALA LUMPUR: Progress on the 3.88km railway bridge across Sungai Kuantan took another step forward with the successful “stitching” of the span that goes above Jalan Kuantan-Sungai Lembing, or Route C4.

China Communications Construction (ECRL) Sdn Bhd (CCC-ECRL), the engineering, procurement, construction, and commissioning contractor for the East Coast Rail Link (ECRL) project, said the achievement was notched on Thursday, at the spot near Kampung Padang, Pahang.

“The highway is one of the busiest in Kuantan, and one that is also flood-prone. To avoid disruptions and ensure the safety of road users, the section was built using the balanced cantilever method, where a 48m continuous beam was constructed in five segments with a final closure segment completing the stretch,” it said in a statement.

“This milestone is the first of its kind along the construction of the 665km ECRL alignment, scheduled for completion in December 2026,” it added.

The construction of the Sg Kuantan Bridge, considered a major bridge, began in July 2020 and is expected to be completed by August 2024.

Just last month, CCC-ECRL inked a supplementary agreement with the Wildlife and National Parks Department (Perhilitan) to improve the implementation of the Wildlife Management Plan, an initiative for wildlife conservation and mitigation works along the entire ECRL alignment.

The ceremony was attended by Perhilitan director general Datuk Abdul Kadir Abu Hashim, Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak, and CCC-ECRL managing director Kong Qi.

In the first memorandum signed between CCC-ECRL and Perhilitan in 2018, more than RM9mil was allocated for Perhilitan’s Wildlife Management Plan.

The recent supplementary agreement covers the extension of the collaboration period to include the construction phase of ECRL, and also the alignment from Kota Baru, Kelantan, to Jalan Kastam (Port Klang), among other environmental protection programmes.

Abdul Kadir said: “Funds pledged will go towards the Wildlife Mana- gement Plan initiatives, which include wildlife mitigation and conflict control, human-elephant conflict study, public awareness and habitat enrichment.”

Meanwhile, Kong said the purpose of the fund is to establish environmental safeguards and ensure that environmentally-friendly initiatives are carried out during the construction of the ECRL.

“We are dedicated to developing the project without endangering the natural habitats of wildlife along the alignment. Several significant steps have been taken by the environmental experts of the ECRL project and the Energy and Natural Resources Ministry, such as improving the alignment and design to reduce the impact to natural habitats as much as possible.

“By tunnelling through forest areas, we avoid cutting forests full of wildlife and damaging the natural habitats. Tunnels with a total length of 15.22km will also be constructed to reduce deforestation of seven forest reserves areas that the ECRL will traverse under,” Kong said, adding that mitigation measures include building 58 tunnels, 128km of viaducts and 20 wildlife crossings.

Through tunnelling and fine- tuning of design, the project was able to reduce forested land usage by 90%, from the initial forecast of 2,000ha of forest land loss, to 276ha.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Malay Chamber of Commerce Malaysia welcomes digital foreign worker quota system, calls for continuous improvements
Study finds flexible work arrangements boost productivity, says HR Ministry
MACC remands 33 individuals, in massive immigration graft sweep
Banting school stabbing suspect to be charged on Friday, say Selangor cops
Form Six student dies after collapsing during school activity in Melaka
Johor polls: Barisan's Bekok candidate favours direct outreach over office meetings
Johor polls: Pakatan's first-time candidate banks on 30 years of local trust in Bekok fight
Cancelled missile deal: Take legal, diplomatic action against Norway, says DPM
Johor polls: Make informed choices, Zahid urges young voters
Police sergeant begins 14-month jail term after losing appeal in bribery case

Others Also Read