PJ mayor orders contractor to provide recovery plan for playground


Playground at Jalan SS23/7 in Taman SEA with substandard upgrades, including chipped cement path, as reported by zone councillor Quratulain. — Photos: IZZRAFIQ ALIAS/The Star

THE contractor of a failed upgrade project on a playground in Petaling Jaya, Selangor, has been instructed to provide a recovery plan soon.

Mayor Datuk Mohamad Zahri Samingon made the order after seeing the poor condition of the playground in Jalan SS23/7, Taman SEA.

The upgrade project is scheduled to be completed this July.

He made the site visit after the matter was raised by councillor Quratulain Atiqah Norzahirul Anuar at MBPJ’s full council meeting in March.

Thanking Quratulain for highlighting the issue, Mohamad Zahri had said at the meeting that he could not accept the contractor’s bad work.

Promising to investigate, he said that he had previously sacked contractors over substandard workmanship even though their projects were at 95% completion.

Mohamad Zahri said that some projects resulted in more problems than expected and this had to stop.

At the full board, Quratulain cited the contractor’s poor workmanship and failure to meet deadlines, adding that several payments had already been made.

Cement on a repaired walking path at the Jalan SS23/7 Taman Sea playground have chipped off.
Cement on a repaired walking path at the Jalan SS23/7 Taman Sea playground have chipped off.

Quratulain said the contractor and those tasked with supervising the project have betrayed the trust of concerned residents and MBPJ.

“I have raised this issue several times at council meetings since the project was implemented in 2025,” she had said, noting that polysheets and empty cement bags had also been buried at the field.

“When I asked the supervisor about it, he said it was done by the workers and claimed he had no knowledge of the matter.”

Much of the project remained incomplete with only about 30% of the work done, she added.

Quratulain had also suggested MBPJ conduct thorough background checks of future contractors and reject those blacklisted by government agencies.

“Impose a waiting period of two years before reconsidering such contractors.

“Ensure companies have clear profiles, relevant experience, good track record and stable finances.”

Quratulain also asked MBPJ to enforce strict timelines for projects, including issuing warnings and terminating contracts for failure to meet deadlines.

“Implement staggered payments based on completed work, to ensure quality and adherence to schedules.

“Overall, the aim is to ensure high quality, accountability and better protection for residents.” — By SHEILA SRI PRIYA

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
playground , failed project , MBPJ , Petaling Jaya ,

Next In Metro News

Breathing new life into disused spaces
Over RM6mil allocated to desilt Klang’s monsoon drains
Helping stamp out drug abuse among youths
Breakfast Day rallies over 70,000 people across six states
From gated alleys to open community spaces
Elevating nation’s beloved staples
Kepong residents want solution to recurrent floods
Johor stadium new theme park exhibit
JB travel agent ordered to pay RM4,990 to couple who cancelled umrah trip
Club boosts partnerships to promote healthcare in Negri

Others Also Read