PETALING JAYA: CBH Engineering Holding Bhd has accepted a work order from Company A for the design, supply, installation and commissioning works of a Consumer Substation (Phase 2) and medium voltage installation and commissioning of works for a data centre in Johor, worth RM59.6mil.
In a filing with Bursa Malaysia, CBH said the contract shall be completed on Sept 19, 2027.
“The scope of works cover design, supply, installation, testing and commissioning of electrical infrastructure for a data centre project, including a high voltage substation package and medium voltage works for the data centre.”
CBH said Company A was incorporated in Malaysia as a private company limited by shares and is principally engaged in activities of providing infrastructure for hosting, data processing services and related activities.