HCM City’s first metro line to run commercially from July next year


HCM City’s first metro line will be operational for commercial use starting from July 2024. — VNA/VNS

HCM CITY (Vietnam News/Asia News Network): HCM City’s first metro line will be operational for commercial use starting from July 2024, city authorities said.

The line is set to be completed by the end of this year, followed by staff training in June 2024, according to the Management Authority for Urban Railways (MAUR).

Certain regulations, standards, and procedures pertaining to system safety certification are yet to be finalised, which has impacted the project’s progress, it said.

The line, connecting Ben Thanh Market in downtown District 1 with Suo Tie Theme Park in Thu Duc City, is currently over 96 per cent complete.

Its underground and elevated sections have been tested, and major stations such as HCM City Opera House and Ba Son are scheduled for completion by the end of this month.

The tracks and depot will be finished by next month, with the remaining work to be completed by December.

The first electric railway line is expected to be fully constructed by the end of this year.

The installation of the project’s electrical and mechanical system will be completed by March 2024, followed by inspections and adjustments to ensure smooth operation.

MAUR has set a target to finish the construction of nine pedestrian bridges connecting the elevated stations by mid-2024, along with system safety certification and training for train drivers and operating staff.

The authority will closely monitor implementation to ensure operations start as planned.

In terms of fares, ticket prices will be determined by the distance traveled.

The proposed minimum fare will be VNĐ12,000 for journeys under 5km, VNĐ14,000 for distances of 5-10km, VNĐ16,000 for 10-15km, and VNĐ18,000 for distances over 15km.

A monthly pass will be available for VNĐ260,000, and there will also be options to purchase tickets for one day or three days, priced at VNĐ40,000 and VNĐ90,000, respectively.

The total cost of the metro project is estimated at VNĐ43.7 trillion. It will span a distance of 19.7km, with 2.6km underground and 11 stations.

The metro line has faced multiple delays. Originally scheduled for completion in 2018, funding issues and the impact of the Covid-19 pandemic have led to ongoing delays.

In a related development, metro line No 2, running from Ben Thành Market in District 1 to Tham Luong Depot in District 12, is also currently undergoing land clearance and technical infrastructure relocation, and is set for completion in 2030.

Subscribe now to our Premium Plan for an ad-free and unlimited reading experience!

Vietnam , HCM , metro ,

   

Next In Aseanplus News

Asean news headlines as at 9pm on Wednesday (Dec 6)
Tariff cuts on electricity to help energise tourism in Cambodia: EAC
TVB star Kenneth Ma addresses rumours of a feud with HK actor Kevin Cheng
Sirul may find himself behind bars again soon
Man charged with outrage of modesty for alleged sexual assault of 2-year-old girl
Vietnam's January-November rice exports hit record high since 1989
Sweden to deepen cooperation with South-East Asia in new trade strategy
Philippines inflation to return to target by December, barring shocks: c.bank gov
Plastic, sweet beverage excise to cause more problems than it solves: Businesses
Cocktails and guest shifts galore as World's 50 Best Bars take over Singapore

Others Also Read