ECRL surpasses 81% progress for Kota Baru - Selangor alignment


PASIR PUTEH: The East Coast Rail Link (ECRL) project is now on track for completion by Dec 2026, with the entire alignment from Kota Baru to Selangor recording a work progress of 81.07% as of March.

The work progress of the project is 90% in Terengganu and 86% in Pahang.

Malaysia Rail Link Sdn Bhd (MRL) chief executive officer Datuk Seri Darwis Abdul Razak said the Kelantan government played an important role in ensuring the smooth implementation of the project, especially in resolving issues related to land acquisition.

"The work progress of the 43km alignment in Kelantan has achieved 88.86%, contributing significantly to the progress of the overall project. The testing and commissioning process is expected to begin in June 2026.

"Track laying works have also shown positive developments, with significant progress achieved in Kelantan, Terengganu and parts of Pahang involving the 400km alignment from Tunjong, Kota Baru, to Maran in Pahang," he said.

He told reporters this after inspecting the progress of the project at the Pasir Puteh ECRL Station site, here on Thursday (April 17).

Darwis said the construction of two ECRL stations in Kelantan, namely in Tunjong and Pasir Puteh, also recorded encouraging progress, reaching 69% and 68% respectively.

Work on both stations is expected to be completed by May 2026.

According to him, most of the issues raised by residents, including flash floods in Pasir Puteh, have been addressed through engagement sessions with the Land and District Office, local authorities and the state government since 2024.

"We are committed to resolving every issue to ensure that this project benefits the people and can be completed on schedule," he said.

The 665km ECRL project crosses the East Coast states of Kelantan, Terengganu and Pahang before connecting Selangor on the West Coast of Peninsular Malaysia.

The ECRL line from Kota Baru to the Gombak Integrated Terminal is expected to be completed on schedule in Dec 2026 and will begin operation in Jan 2027. - Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Disabled teen, mum rescued after flood hits Teluk Intan home
Trailer lorry driver killed in four-vehicle crash in Perak
Lima '25 opens in Langkawi, showcasing cutting-edge aerospace, maritime tech
Two men nabbed in Ipoh with drugs
Old mortar shell discovered at Penang construction site
INTERACTIVE: Tapirs top roadkill list in Malaysia
DBKL embraces AI for traffic management
Drones to monitor gas pipelines
Work together to overcome summit jams, say business groups
PIA expansion work set to meet end-of-year target

Others Also Read