KUALA LUMPUR: The Aerotrain Replacement Project at Kuala Lumpur International Airport (KLIA) is slated to be completed by Jan 31, 2025 which is ahead of the project’s original planned completion date, says Malaysia Airports Holdings Bhd (MAHB).
The airport operator said this expedited timeline was finalised through a contract signed on June 14 between Malaysia Airports (Sepang) Sdn Bhd (MA Sepang), Alstom Transport Systems (Malaysia) Sdn Bhd, and IJMC-Pestech JV, a joint venture between IJM Construction Sdn Bhd and Pestech Technology Sdn Bhd.