JB-S’pore RTS Link project reports steady progress, nears 80% completion


JOHOR BARU: The construction of the Rapid Transit System (RTS) Link project between Johor Baru and Singapore is progressing as scheduled, reaching 77.61% completion as of May 31.

Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) said that the maintenance depot, a key part of the railway infrastructure located in Wadi Hana, has achieved 82.14% progress and is set for system installation by the end of the year.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Bersama is not a ‘Trojan Horse’ for BN or PAS, says Rafizi
Hajiji orders districts to unlock agriculture, tourism and industry potential
Third link's inclusion in structure plan only indicative, work won't begin immediately, says Penang CM
Local grain maize productions aims to reduce import dependence, improve food security, says Mat Sabu
MMEA activates SAR ops after Thai fisherman falls overboard in Kedah waters
Key institutional, economic reforms need to be implemented as soon as possible, says Gobind
Three police reports lodged over vandalised statues at Bukit Tinggi place of worship
Let the current unity government go its full term, says LDP chief
Not easy for DAP to step back after 'tasting power', says Rafizi
Penang Hill funicular service to close from Jan 4-10 for scheduled maintenance

Others Also Read