JOHOR BARU: The construction of the Rapid Transit System (RTS) Link project between Johor Baru and Singapore is progressing as scheduled, reaching 77.61% completion as of May 31.
Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) said that the maintenance depot, a key part of the railway infrastructure located in Wadi Hana, has achieved 82.14% progress and is set for system installation by the end of the year.