RM8.4bil capacity charge to Perak covers water plant building costs over 40 years, says Penang CM


filepic

GEORGE TOWN: The RM8.4bil capacity charge payable over 40 years under the Bulk Water Supply Agreement (BWSA) with Perak represents deferred payments to recover the construction costs of a water treatment plant built specifically to supply water to Penang, says Chow Kon Yeow (pic).

The Penang Chief Minister said the charge, amounting to RM210mil annually, was an "availability payment" for the plant's capacity.

It is a standard payment mechanism in long-term bulk water supply agreements and is separate from charges for the actual volume of water supplied, he said.

He said the water treatment plant, with a capacity of 500 million litres per day (MLD), was constructed exclusively to supply the Penang Water Supply Corporation (PBAPP), at an estimated construction cost of RM3bil.

ALSO READ: Penang-Perak water deal to cost RM210mil a year for 40 years plus RM1.70 per cubic metre of treated water

"When financing costs and plant renewal works over the 40 years are taken into account, the total amount comes to RM8.4bil," he said in a statement on Thursday (Nov 19).

"This figure has undergone scrutiny and review by financial consultants appointed to conduct due diligence on the project.

"Prasarana Air dan Irigasi Perak (PAIP) is responsible for securing the financing and bearing the construction risks, while PBAPP is not required to make any upfront payments or capital contributions to PAIP."

On Wednesday (Nov 18), Bagan MP Lim Guan Eng, a former Penang chief minister, questioned why PBAPP was required to pay RM210mil annually for 40 years, amounting to RM8.4bil, despite no treated water having been supplied to Penang to date.

ALSO READ: PBA to buy treated water from Perak under RM24.6bil long-term supply deal

Chow, who also chairs PBA Holdings Berhad (PBAHB) and PBAPP, explained that the plant's construction costs would be recovered through the annual capacity charge over 40 years, beginning when water supply commences.

This arrangement would spread the financial commitment over the agreement's duration, making the payments more manageable for PBAPP, he added.

He said the BWSA also provides for a separate supply charge, amounting to RM16.2bil of the total RM24.6bil payable under the agreement, which represents the cost of the water itself.

Addressing concerns raised by five PBAHB directors who had expressed reservations about certain aspects of the agreement, Chow said they generally acknowledged the need to secure the water supply but had raised concerns over the payment terms.

These concerns included the possible invocation of the "Perak State Interest Clause" and the implications of a prolonged suspension of water supply.

Chow stressed that several safeguards had been incorporated into the agreement to protect Penang's interests, particularly those of PBAPP.

He said that under the agreement, PBAPP is only required to pay the supply charge based on the actual volume of water received that meets the stipulated quality standards.

Furthermore, PAIP is required to compensate PBAPP at an agreed rate for every cubic metre of water shortfall or supply that fails to meet the required quality standards, as verified by an independent laboratory.

ALSO READ: PBA shareholders approve RM24.6bil Perak water deal with 98% support

He said PBAPP also retained the right to terminate the agreement and claim damages if PAIP breached its contractual obligations and failed to rectify the breach within 90 days.

In the event of a water supply suspension lasting more than three months, provided the disruption was not caused by PBAPP, either party would be entitled to request a renegotiation of the agreement. This could include referring the matter to their respective state governments for mediation.

"Either party may terminate the agreement only if the renegotiations fail to reach an agreement after a further three-month period.

"In such circumstances, PBAPP would only be required to make a one-off payment equivalent to the outstanding balance of the capacity charges, discounted at a rate of 4% per annum, instead of continuing to pay RM210mil annually until 2072," Chow explained.

He stressed that the BWSA, which provides for balanced allocation of risks between PBAPP and PAIP, was a strategic measure to secure Penang's long-term water supply, particularly as the state's existing surface water resources are projected to reach full utilisation by 2030. – Bernama

 

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Newborn baby girl found stabbed, buried behind house in Pantai Remis
Ten Melaka assemblymen sworn in as exco members
Motorcyclist survives after being swept away in Bentong flash flood
Anwar pays tribute to Wan Ahmad Dahlan for service to nation
Stop sharing unverified info, says Perak MB on claims of assembly dissolution
Police rule out foul play in Kuala Kangsar boarding school student's death
Rise in elephant sightings highlights decade-old problem in Telupid
BN backbenchers demand answers over alleged leak of Pardons Board minutes
Fire breaks out along conveyor belts at Tanjung Bin power plant in Pontian
Sabah urged to address four key areas for smooth Native Court Enactment rollout

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read