A-G's report: 36 water supply projects in Sabah, Sarawak delayed by up to seven years


KUALA LUMPUR: Some 36 rural water supply projects in Sabah and Sarawak, with a combined cost of over RM1.6bil have been delayed by up to seven years and left thousands of households without clean and treated water, the Auditor-General's Report 2/2024 has revealed.

The projects were approved in 2016,2017 and 2018, according to the audit on the Rural and Regional Development Ministry.

Twelve projects are in Sarawak with a combined cost of RM888.32mil and 24 in Sabah at a total cost of RM758.85mil.

As a result, 9,608 households in Sarawak do not have clean and treated water while 22,621 households are affected in Sabah.

The ministry said that the delays were due to the need to appoint a consultant; design preparation and approval which takes a long time; protests from locals; changes in government procurement policies; changes in work scope and the performance of contractors as well as lockdowns ensuing from the Covid-19 pandemic.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Jho Low still wanted by Singapore police amid US clemency efforts
Boy dies after being hit by SUV in Rembau
Malaysia-Japan ties more crucial in an uncertain world, says Anwar
Unmo says Federal unity govt agreement does not bind party at state level
Johor JPJ to equip more officers with body-worn cameras
Foreigners suspected of doing business under Malaysian names nabbed
Malaysia, Japan agree on energy security, nuclear and critical minerals cooperation
Govt spending RM3.5bil a month on fuel subsidies, says Finance Ministry
Bomba reviewing SOPs for mountain climbing, other extreme sports
MetMalaysia warns of thunderstorms in several states until 9pm (June 10)

Others Also Read