A-G's report: 36 water supply projects in Sabah, Sarawak delayed by up to seven years


KUALA LUMPUR: Some 36 rural water supply projects in Sabah and Sarawak, with a combined cost of over RM1.6bil have been delayed by up to seven years and left thousands of households without clean and treated water, the Auditor-General's Report 2/2024 has revealed.

The projects were approved in 2016,2017 and 2018, according to the audit on the Rural and Regional Development Ministry.

Twelve projects are in Sarawak with a combined cost of RM888.32mil and 24 in Sabah at a total cost of RM758.85mil.

As a result, 9,608 households in Sarawak do not have clean and treated water while 22,621 households are affected in Sabah.

The ministry said that the delays were due to the need to appoint a consultant; design preparation and approval which takes a long time; protests from locals; changes in government procurement policies; changes in work scope and the performance of contractors as well as lockdowns ensuing from the Covid-19 pandemic.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Teenager drowns trying to save friend in Sungai Sedim, Kedah
Chinese national detained for installing Jalur Gemilang upside down in Senai
No more pig farms in Tanjong Sepat, decrees Selangor Ruler
Border agents seize RM78,180 in undeclared cash at Rantau Panjang ICQS
Kelantan told to postpone travel to southern Thailand following bomb attacks
Biker dies in multi-vehicle crash near Ayer Hitam, Johor
Blast victim an intern scheduled to finish training in three days
Former political aide Sayed Amir demanded RM19mil 'lump sum' bribe, witness tells court
Sultan Sharafuddin decrees for firm action against LBGT activities in Selangor
Akmal to abide by Ahmad Zahid, Ab Rauf's decisions

Others Also Read