Puchong landslide: Phase two of piling work 50% complete, says the police


KUALA LUMPUR: Phase two of the sheet piling work in the drain area near the landslide location at Jalan Wawasan 3/9 Taman Wawasan in Puchong is now 50% complete.

Serdang OCPD Asst Comm A. Anbalagan said that 590 sheet piles, including 375 in the phase one area, have been installed to help stop any soil movement.

"The estimated time of completion by the contractor is two weeks, depending on current weather conditions,” he told Bernama on Tuesday (Jan 2).

Even though it has been raining frequently in the past few days, there has been no soil movement reported in the area.

The landslide that occurred on Dec 16 forced 29 residents from nine terrace houses in Taman Wawasan Puchong to evacuate due to safety concerns. - Bernama

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Johor polls: Pakatan top guns to meet June 29 to finalise manifesto, says sec-gen
Pakatan fielding top talent for Johor polls to ensure state-Federal alignment, says Saifuddin
Johor polls: Set disappointment aside if not chosen to contest, says Ahmad Zahid
Nine stalls, vehicles destroyed in Sandakan fire
Pakistani man arrested for allegedly running fake clinic, posing as ‘unlicensed doctor’ in Subang
Johor polls: Home Ministry sets up task force to tackle polling day disruptions at Causeway
Johor polls: Focus on our service to the people instead of personal attacks, Johari tells BN candidates
Johor polls: MCA will face campaign calmly, says Dr Wee at Yong Peng nomination centre
Muhammad Faris installed as 11th Undang of Sungei Ujong
PM Anwar to launch LRT3 Shah Alam line tomorrow

Others Also Read