Pond fully operational, handover end-November


Solar-powered lights line a completed section of the planned 2km walking path around Kampung Bohol Flood Detention Pond, where landscaping work is still underway. — ART CHEN/The Star

Kampung Bohol Flood Detention Pond is now fully operational, with no flash floods reported in surrounding areas since it came into service a few months ago.

A spokesperson for the contractor said landscaping work on an adjoining recreational park was underway, including construction of a 2km walking path, of which about 600m – or 30% – have been completed.

Solar-powered lights have been installed along the concrete path, and about 1,000 shade trees are slated to be planted across the park.

ALSO READ: Data centre mooted beside Bohol flood detention pond

Planned species include rain trees, golden shower trees, bungor, trumpet trees, jambu air and gelam.

“Together, they will provide shade and greenery, add seasonal colour with their flowers and fruit, and provide habitats and food sources for urban wildlife,” the spokesperson said.

A moon-shaped bridge is also being built to link residents from Kinrara, Bukit Jalil and Jalan Kelang Lama to the park.

“We are using solar power throughout the park.

“Lights along the walking path, the guardhouse and even the pumps for the irrigation system will all run on solar energy,” he said.

The spokesperson said Sungai Kuyoh, Sungai Bohol and Anak Sungai Bohol channelled floodwater into the pond via three inlets before it is discharged into Sungai Klang.

“The pond is fully functional. Since it began operating, there have been no reports of flash floods in the surrounding area,” he added.

The update follows a delay in the project’s expected handover to the government, which has been pushed from October to the end of November.

According to the spokesperson, project costs had risen from about RM40mil to more than RM70mil after Drainage and Irrigation Department (DID) requested additional landscaping and the walking path.

The contractor aims to hand over the site by end-November, with a tree-planting ceremony planned to mark the occasion.

Once completed, the pond – which does not require continuous on-site monitoring – will be managed by DID, while Kuala Lumpur City Hall (DBKL) will oversee the park.

Upgrading works began in mid-2025 following the clearance of squatter settlements, though progress was slowed by prolonged approval processes, restricted working hours, persistent heavy rain and difficult ground conditions.

A private developer is carrying out the upgrade as part of a 2024 land alienation deal, which originally stipulated that the pond be completed within five months before work on the surrounding residential plots could begin.

In May, Minister in the Prime Minister’s Department (Federal Territories) Hannah Yeoh reiterated that no residential development linked to the deal would be permitted until the pond upgrade was finished, in line with the “Upgrade First, Build Later” rule.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Metro News

Driving awareness of early cancer detection
Data centre mooted beside Bohol flood detention pond
Muddy fun in Perlis padi fields�
MBPJ: Keep clean, don’t attract crows
‘Understanding the root cause of homelessness is essential’
‘Positivity keeps startup running’
Cheated of RM12,000 by travel agent, women still on for Vietnam holiday
Ageing population among PJ councillor’s priorities
Banking on social impact to empower communities
PJ Section 17 folk weary of floods

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read