Penang court back in session after ceiling collapse


By N. TRISHAThe Star
The first floor near the Penang High Court staircase cordoned off following a ceiling collapse.

Old trusses in heritage building will require repair, says exco

COURT proceedings have resumed at the Penang High Court’s heritage building in George Town following the ceiling damage incident last week.

Penang Bar committee civil practice and court liaison subcommittee co-chairman S. Gowri said only High Court 1 and High Court 2 rooms, on the first floor near the damaged ceiling, have been cordoned off.

“The ground floor and the remaining areas of the first floor are fully functional.

“Members are advised that the grand staircase entrance facing Lebuh Light remains closed until further notice,” she told StarMetro when contacted.

Gowri said cases scheduled at High Court 1 and High Court 2 have been relocated to the Technology Court on Level 2 and the Malaysian Anti-Corruption Commission Court on Level 1 respectively at the annexe building next to the Penang High Court.

She added that the situation at the courthouse is not as serious as initially thought and that three courtrooms have resumed operations.

Last Tuesday, it was reported that part of the ceiling at the restored 123-year-old Penang High Court building collapsed over the weekend, with planks and debris littering the first floor.

Penang infrastructure committee chairman Zairil Khir Johari said the Public Works Department (JKR) has inspected the site with its architects, structural engineers and the building team.

Fallen planks littering the staircase.
Fallen planks littering the staircase.

It discovered that two of the six timber roof trusses over that area had failed.

“Initial observations show deterioration of the timber, including signs of termite damage.

“The exact cause has not been confirmed and needs a detailed technical assessment, including the truss joints and supporting walls.

“This means it is structural damage to the roof system in one section,” he said.

“Part of the ceiling and cornice came down.

“Fortunately, no one was hurt and the detailed inspection will confirm the condition of the remaining trusses and whether any other part of the building is affected.

“Long-term repairs will follow the requirements for a heritage building,” he added.

Zairil said JKR has carried out a detailed inspection of the remaining roof trusses and the rest of the building.

On who will be responsible for fixing the damages, Zairil said the upgrading contract (Federal project) covered replacing only some of the roof trusses.

“That scope was set based on the consultant’s dilapidation report and the main contractor’s inventory of damaged trusses.

“JKR is now reviewing the contract records, including the obligations of the contractor and the consultants.

“If anyone is found responsible, they will be held accountable.

“The building is currently maintained under a facilities management contract appointed by the Legal Affairs Division.

“Right now the priority is making the building safe and getting the court back in operation,” he said.

Lawyer Cheah Eng Soon, who was scheduled to attend a civil case hearing at the High Court on Tuesday said he was informed by the Bar Council that the case was postponed due to the ceiling damage.

“My client was given a new hearing date, and the case will now be heard online.

“I am just grateful that no one was injured, as the incident happened over the weekend,” he said.

Cheah said despite restoration works, “it is not built with stronger materials such as concrete because it is a heritage building.

“It is a beautiful old building, but perhaps not the most structurally stable.

“As long as the damage is fixed, it is still good to use,” he said.

In August 2024, upgrading and restoration works on the building were completed after nearly three years.

It underwent a much-needed upgrade and conservation effort to address issues such as leaking roofs, termite damage, humidity problems, fungal growth and water stains costing RM18.9mil.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Metro News

PJ Section 17 folk weary of floods
Data centre mooted beside Bohol flood detention pond
‘Understanding the root cause of homelessness is essential’
‘Positivity keeps startup running’
Cheated of RM12,000 by travel agent, women still on for Vietnam holiday
Ageing population among PJ councillor’s priorities
Pond fully operational, handover end-November
AUCTION CARNIVAL TO FEATURE UP TO 1,000 LOTS
Online switch reminder for Iskandar Puteri businesses
Repair of damaged drain embankment in Tmn Melawati to take four weeks

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read