REPAIR works on a drainage embankment damaged by soil movement in Taman Melawati, Ampang, Selangor, are expected to begin soon and take four weeks to complete.
Ampang Jaya Municipal Council (MPAJ) received a complaint about damage near houses along Jalan F1 in the township before inspecting the site last week, it said in a social media post.
The inspection found that soil movement had damaged the side of a drainage channel, the council said.
In a follow-up statement, MPAJ said its Engineering Department had conducted preliminary inspection and assessment of the affected area.
A contractor had been appointed to carry out the repairs, which were currently in preparation stage, it said.
“Works are scheduled to begin soon and expected to be completed within four weeks of commencement.”
MPAJ said it would continue monitoring the works to ensure the safety of residents and public infrastructure.
In a separate incident, a fallen tree was reported along Jalan Perdana 10/1 in Pandan Perdana, with the MPAJ Enforcement Department receiving a complaint about the incident at 8pm.
The council said action was taken to ensure the affected area was safe and that road users were not obstructed.