PETALING JAYA: CBH Engineering Holding Bhd has accepted a work order from Company A for the design, supply, installation and commissioning works of a consumer substation (Phase 1) at a 275 kilovolts data centre or DC in Johor, worth RM29.69mil.
In a filing with Bursa Malaysia, the electrical engineering service provider said the contract period will be effective from April 27, 2026 until the estimated practical completion date of Sept 30, 2026.
“The scope of works includes, inter alia, high-voltage and medium-voltage electrical works, installation of substation equipment and systems, cabling and associated infrastructure, earthing and lightning protection systems, as well as integration with Tenaga Nasional Bhd
’s metering and information and communication technology systems, together with all related ancillary and preliminary works necessary for the completion of the project,” it said.