ECRL achieves 93% construction progress in February


--fotoBERNAMA

GOMBAK: The East Coast Rail Link (ECRL) project has reached 92.62% completion as of February 2026, in line with the schedule to complete the Kota Bharu-Gombak alignment by the end of this year and begin commercial operations in January 2027.

Finance Minister II Datuk Seri Amir Hamzah Azizan said the ECRL alignment from Gombak to Port Klang in Selangor will be completed by December 2027 and will become fully operational in January 2028.

Moreover, he said that the commercial operation of electric multiple unit trains and electric locomotives will open a new chapter in strengthening the ECRL as a green transportation mode for passengers and cargo, spanning a 665km electric rail network across the East Coast states and Selangor.

“The ECRL project has recorded another important milestone today with the completion of the 519km main track alignment from Kota Baru to Gombak, ahead of schedule. — Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
ECRL , transport , infrastructure , construction

Next In Business News

Pos Malaysia sees 15-20% rise in Raya parcels, hijabs among top items sent
TPG establishes One Aged Care to deliver integrated care services
Ringgit opens firmer vs US$ on improved sentiment
Bursa rises slightly on US tech rally, oil crisis remains in focus
Petrobras to purchase PETRONAS' stakes in two offshore fields for US$450mil
Singapore's February exports rise 4.% y-o-y, lower than expected
Trading ideas: IJM, Sunway, TNB, TM, Keyfield, Dialog, Aneka, Fitters, Pharmaniaga, Advancecon, Sunway Healthcare
Wall Street ends higher as traders return to AI stocks
EcoWorld to leverage on JLG’s landbank in Johor
Bright prospects for tech

Others Also Read