ECRL achieves 93% construction progress in February


--fotoBERNAMA

GOMBAK: The East Coast Rail Link (ECRL) project has reached 92.62% completion as of February 2026, in line with the schedule to complete the Kota Bharu-Gombak alignment by the end of this year and begin commercial operations in January 2027.

Finance Minister II Datuk Seri Amir Hamzah Azizan said the ECRL alignment from Gombak to Port Klang in Selangor will be completed by December 2027 and will become fully operational in January 2028.

Moreover, he said that the commercial operation of electric multiple unit trains and electric locomotives will open a new chapter in strengthening the ECRL as a green transportation mode for passengers and cargo, spanning a 665km electric rail network across the East Coast states and Selangor.

“The ECRL project has recorded another important milestone today with the completion of the 519km main track alignment from Kota Baru to Gombak, ahead of schedule. — Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
ECRL , transport , infrastructure , construction

Next In Business News

Ringgit opens slightly higher against US$ amid Middle East developments
Bursa bounces higher as corporate results trickle in
Trading ideas: Southern Score, Malakoff, WCT, Censof, L&G, Oppstar, Alam Maritim, HE, MKH, Sports Toto, SunCon, Capital A, KLK, Pharmaniaga, 99 Speed Mart
Nasdaq leads equity losses with oil, borrowing costs in focus
SC, Bursa Malaysia propose LEAP market 2.0 to boost MSME fundraising
Central banks to step up gold-buying, aiding prices
TNB launches maiden national grid-linked Bess
Firmer CPO prices to bolster Johor Plantations
Swift Haulage pins hopes on second-half rebound
Domestic demand to keep economy on steady route

Others Also Read