ECRL achieves 93% construction progress in February


--fotoBERNAMA

GOMBAK: The East Coast Rail Link (ECRL) project has reached 92.62% completion as of February 2026, in line with the schedule to complete the Kota Bharu-Gombak alignment by the end of this year and begin commercial operations in January 2027.

Finance Minister II Datuk Seri Amir Hamzah Azizan said the ECRL alignment from Gombak to Port Klang in Selangor will be completed by December 2027 and will become fully operational in January 2028.

Moreover, he said that the commercial operation of electric multiple unit trains and electric locomotives will open a new chapter in strengthening the ECRL as a green transportation mode for passengers and cargo, spanning a 665km electric rail network across the East Coast states and Selangor.

“The ECRL project has recorded another important milestone today with the completion of the 519km main track alignment from Kota Baru to Gombak, ahead of schedule. — Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
ECRL , transport , infrastructure , construction

Next In Business News

Japan's Nikkei rises on tech rally, stronger yen lifts JGBs
Indonesia to cut ride-hailing companies' maximum commission taken from drivers to 8%
Take Five: Sell in May? Let's find out
Asia shares find hope in tech resilience, oil off peak
SME Corp empowers digitalisation, automation of MSMEs
Yayasan Peneraju fast-tracks SPM leavers into chartered accountancy
ANZ says Australia likely to avoid recession; flags prolonged impact of Middle East war
Japan's factory activity growth hits 4-year high on stockpiling, PMI shows
South Korean April exports rise 48.0% y/y as chip boom extends
Japan warns yen speculators it stands ready to intervene again

Others Also Read