Laos-China railway bed in place, over 20 per cent track laid


VIENTIANE, Aug 3 (The Vientiane Times/ANN): Construction of the route and foundations for the Laos-China Railway has been achieved, and the laying of the tracks is over 20 percent complete, according to a leading official with the megaproject.

Director General of the Laos-China Railway Co Ltd, Xiao Qianwen updated Prime Minister Thongloun Sisoulith on the progress of the 414.3km-project during a visit to inspect construction in Xay village, Xaythany district, Vientiane last week.

From Vientiane to the Laos-China border in Luang Namtha province, “the running of the track foundation is 100 percent finished,” he said, adding that placement of the steel tracks was 21.4 per cent completed.

Currently, 71 out of the 75 tunnels have been drilled, and 88 per cent of railway bridge construction has been completed. The installation of high voltage electricity poles is 57.4 per cent complete.

However, some stations have not yet started construction due to the severe impact of the Covid-19 outbreak, and several areas are still in the process of mediation with landholders.

According to a member at the National Assembly (NA)’s 8th legislature last month, there was still a steady stream of public comment regarding unsettled compensation in Oudomxay and Vientiane provinces.

Therefore, the NA recommended that relevant committees of both provinces continue working with those affected to come to a satisfactory resolution.

During PM Thongloun’s visit, he also emphasised that the company and related sectors mediate with the people living near the train stations in Vientiane and Thanalaeng 12.7 km along the track to resolve problems.

The implementation of the Laos-China railway construction must be done in accordance with the signed agreement between the governments of Laos and China.

The investment project between both governments will see passenger trains running at 160km per hour from Vientiane to the Boten-Mohan border through the four provinces of Vientiane, Luang Prabang, Oudomxay and Luang Namtha.

The 414.3-km railway will feature 198 km of tunnels and 62 km of bridges, and when operational, the journey from Vientiane to the Boten border crossing in Luang Namtha province will be reduced from the present two days by road to less than three hours by train.

The railway is scheduled for completion at the end of 2021. - Vientiane Times/Asian News Network

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Aseanplus News

Ram Temple donation scam: Were stolen gold ornaments melted into biscuits? India's Special Investigation Team reviews Trust records
Malaysia continues to face an onslaught of racist politics, says Anwar
Vietnam posts trade deficit of US$16.65bil in first six months
Chiang Mai’s Tham Luang Mae Sap reopens to visitors
Lorry driver trapped after multi-vehicle accident on Singapore's AYE; four taken to hospital
Johor polls: Teoh Beng Hock’s sister campaigns for Muda, PSM, Bersama
Chinese wife sucks venom from husband’s hand after cobra bite, ending up poisoning herself
BTS named La Plata 'honoured guest' ahead of Argentina concerts
Anwar urges Johoreans abroad to return home, vote in state elections
Johor to benefit if same coalition helms Federal and state govts, says Nga

Others Also Read