KUALA LUMPUR: There are currently 23 schools in Pahang with buildings classified under Scale 7, the category for dilapidated schools, says Deputy Education Minister Wong Kah Woh.
He said 13 of these schools had been approved for dilapidated building replacement projects under the Malaysia Plans since 2022, while the remaining 10 were being considered in phases, subject to technical assessments, project feasibility and the availability of funds.
Wong was responding to Salamiah Mohd Nor (PN-Temerloh) in the Dewan Rakyat, who asked the ministry to state the total number of schools in Pahang categorised as dilapidated according to scale and district, as well as the number approved for reconstruction or upgrading, including their implementation status and completion targets.
He noted that of the 13 redevelopment projects for dilapidated buildings mentioned earlier, five projects had already been completed, four were in the pre-implementation phase, and another four were in the construction phase.
All of these projects currently under construction are being implemented by the Public Works Department (PWD).
In a supplementary question, Salamiah asked whether the ministry had a specific policy to prioritise the upgrading of dilapidated schools and what monitoring mechanisms were in place to ensure the safety of students and teachers.
Wong said school buildings were continuously monitored by the District Education Office (PPD) and the State Education Department (JPN) to determine whether they had reached Scale 7 status.
"Furthermore, if we have buildings that have reached Scale 6, we will carry out large-scale maintenance so that they do not subsequently fall into the Scale 7 category. That is one of the government's efforts," he said during question time on Tuesday (Nov 17).
"Additionally, over the past two years, the Ministry of Education has also received approval for an initiative that we refer to as Renovation and Upgrading (Ubah Suai Naik Taraf - USNT). This is on top of, or in addition to, the maintenance allocation we have every year.
"This year, the USNT allocation for Peninsular Malaysia alone is RM100mil, which is on top of the existing maintenance allocation.
"Regarding the question on dilapidated schools, I would also like to inform you here that since 2023, every year we have allocated substantial funds for the reconstruction of buildings involving schools with dilapidated structures.
"This demonstrates the commitment of the government to ensure that we can address schools with dilapidated buildings, and at the same time, alongside other efforts, we can reduce the issue of dilapidated schools that we have faced all this while," he said.
In another supplementary question, Mohd Kurniawan Naim Moktar (BN-Kinabatangan) asked whether the ministry had a target to achieve zero dilapidated schools and sought clarification on project monitoring mechanisms, including the use of multiple subcontractors in school construction projects.
Wong said the number of dilapidated schools was dynamic.
"Every year it changes from time to time, where if there are upgrades or reconstruction of dilapidated buildings, those schools are removed from the list. At the same time, however, we also try to prevent other schools with Scale 6 buildings from dropping to Scale 7 and becoming dilapidated schools," he said.
He said recommendations from PWD Malaysia, PWD Sabah and PWD Sarawak played a crucial role in determining whether school buildings should be demolished and rebuilt, with the ministry seeking funding for such projects through future development plans.
"What I have observed over the past few years is that for schools where we have a recommendation from PWD, we will indeed try to secure a budget in the upcoming rolling plan," he said.
On project monitoring, Wong said the ministry had two committees overseeing development projects: the Ministry Development Action Committee, chaired by the ministry's secretary-general and which meets monthly, and the Ministry Development Action Council, chaired by the Education Minister and which meets twice a year.
He said both committees worked closely with PWD and other agencies to ensure school development projects were implemented properly and completed according to plan.