ALOR SETAR: The long-delayed Sungai Petani Racing Circuit project is 78% complete in its initial development phase, after a two-year suspension due to a Malaysian Anti-Corruption Commission (MACC) investigation.
Kedah Mentri Besar Datuk Seri Muhammad Sanusi Md Nor said the initial RM16mil phase, covering infrastructure works, car park facilities and a drag racing circuit, was expected to be completed by June 2027.
"The project was suspended from August 2023 to August 2025 following a MACC investigation, before a decision of No Further Action (NFA) was issued," he said in reply to Teh Swee Leong (DAP-Kota Darul Aman), who asked about the project's implementation timeline, physical progress and expenditure since its inception, at the State Assembly sitting on Monday (Nov 16).
Muhammad Sanusi said that following the NFA decision and Permodalan Kedah Berhad's (PKB) withdrawal from the project in November 2024, Open Road (SP Circuit) Sdn Bhd and its contractor had taken the initiative to resume work using their own financing through a Private Finance Initiative (PFI).
"The overall development cost is estimated at RM46mil, comprising RM16mil for the initial phase and a further RM30mil for the construction of buildings and main structures.
"The current development is fully financed by private funds through the PFI mechanism, without any government allocation for the construction works currently underway," he said.
Muhammad Sanusi said the project had originally received RM30mil in federal funding through the Youth and Sports Ministry.
"Of this amount, RM10mil was spent by the previous administration on site clearing, land preparation and access road construction between 2017 and 2019," he said.
He added that the remaining RM20mil had yet to be utilised, and no additional government funding had been approved for the project. - Bernama