Temporary traffic diversion activated on KL-Karak Expressway


IPOH: A temporary traffic diversion is in place along KM25.75 to KM26.4 of the Kuala Lumpur-Karak Expressway heading towards Kuantan to facilitate construction for the East Coast Rail Link project.

Malaysian Highway Authority (LLM) Director-General Datuk Sazali Harun said the diversion redirects the existing three-lane carriageway to a one-way lane on the opposite side towards Kuala Lumpur.

This maintains a three-lane capacity to ensure smooth traffic flow during the diversion.

"The Traffic Management Plan design has been reviewed and approved by a road safety auditor through the Stage 4 Part 1 Road Safety Audit.

"The next audit, RSA Stage 4 Part 2, will be carried out on Wednesday (July 30) to assess compliance during implementation and to propose improvements based on construction progress," he said in a statement on Thursday (July 17).

He added that LLM, together with concessionaire AFA PRIME Bhd and Malaysia Rail Link, has been conducting continuous monitoring since the diversion's activation.

"The latest monitoring carried out on Monday (July 14) showed that traffic at the location remained orderly, controlled and smooth."

He advised road users to adhere to safety signage at the site and to plan their journeys in advance to avoid congestion.

 
 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

King, Queen extend Father's Day greetings
Victim who fell from Sendayan school had asked permission to go to the toilet
Felda Settlers’ Day celebration to go on in Johor, says caretaker exco member
Take stern action against firms in Daya Kerjaya 2.0 fraud case, says Lam Thye
Weak earthquake strikes Batu Pahat waters, says MetMalaysia
Navigating fatherhood in today’s digital age
Waterspout�wreaks havoc in Bercham
Singer Khadijah credits the press for her success
Celebrating fathers beyond gifts
‘Turkmenistan gas deal proves neutrality pays off’

Others Also Read