Works Ministry to carry out RM200mil flood mitigation works on LPT1


KUALA LUMPUR: The Works Ministry will carry out immediate flood mitigation works in 14 locations along the East Coast Expressway Phase 1 (LPT1) with an allocation of RM200mil to prevent floods from recurring.

Works Minister Datuk Seri Alexander Nanta Linggi said four incidents of flooding have occurred along LPT1 since it first opened in 2004.

"Flooding occurred in 2007, 2014 and twice in 2021, namely in January and December, which caused the expressway to be closed to all types of vehicles for several days.

"Ten flood-prone locations have been identified - at Kilometre (KM) 84.7, KM112, KM113, KM114, KM115, KM116, KM117, KM124, KM126 and KM198. Four more locations at risk of flooding have also been identified, at KM156, KM178, KM242 and at Ramp A, Jabor Junction," he said in a Facebook post Wedneday (July 19).

He visited LPT1 in Temerloh, Pahang on Wednesday, accompanied by Works Ministry secretary-general Datuk Seri Hasnol Zam Zam and Malaysian Highway Authority director-general Sazali Harun.

"I have been briefed and seen the progress of this project. Currently, earthworks at KM117 and KM124 are being carried out and expected to be completed in October 2024," he added. - Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

Papagomo remanded two days until May 2
Civil servants to get over 13% pay hike, says Anwar
Some employers still not complying with minimum wage order, says MTUC
King and Queen: Workers driving force of Malaysia's progress
Debit and credit cards can now be used at RapidKL stations
Promoting peace and a healthy lifestyle in the spirit of Kaamatan
Water supply firm CEO, owner held for bribery and false claims in RM3.3mil project
Dr Wee pays tribute to the country's workers on Labour Day
Police arrest five over death of baby girl in Johor
KKB by-election: Azmin unsure on Takiyuddin's absence from Perikatan ceramah

Others Also Read