The sewage pipe installation works at the intersection of Jalan Semangat and Jalan Dato Abdul Aziz in Petaling Jaya, Section 14 is delayed due to technical problems.
FURTHER delays are expected in the sewerage project at the intersection of Jalan Semangat and Jalan Dato Abdul Aziz in Section 14, Petaling Jaya due to technical difficulties.
Tunnels drilled from two sides did not align properly to install the sewerage pipes and there is a need to create a new alignment for the affected 126m stretch.