In high gear to complete 233km West Coast Expressway


The section of WCE recently open - A major Highway leading to Lumut and Pangkor

AMIDST all the hoopla surrounding the possible buyout of PLUS Malaysia Bhd, the other long stretching highway in Peninsular Malaysia has been making some notable progress.

While West Coast Expressway Holdings Bhd (WCE) has been perceived as having faced numerous delays and challenges with its land acquisitions, its CEO Datuk Neoh Soon Hiong says the company is in high gear to complete the 233km expressway connecting Banting in Selangor to Taiping in Perak.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
West Coast Expressway , complete , PLUS , WCE , MWE , NSE ,

Next In Business News

Malaysian palm oil stockpiles balloon to record on output surge
Jati Tinggi bags RM15.7mil TNB contracts for cable works
Go Hub Capital bags RM64.79mil KTMB ticketing system contract
West River secures RM17.5mil E-Metro Logistic Park subcontract
Yinson secures four-year FPSO extension worth US$600mil
Citaglobal unit bags RM29mil Thailand waste-to-energy project contract
Ringgit ends higher against Asean currencies, eases against US dollar
Southeast Asian property developers brace for slower cycle
Asteel Group secures RM15.8mil Shah Alam logistics complex job
IJM appoints Johan Idris as its chairman

Others Also Read