PHNOM PENH: Cambodia has announced plans for the construction of a 120-kilometre power transmission line that will connect clean solar energy to Kandal, Kampong Chhnang and Pursat provinces.
The 230-kilovolt line, implemented by Electricité du Cambodge (EDC), includes the construction of two new substations and the expansion of two existing ones to strengthen the national electricity grid.
Minister of Mines and Energy Keo Rottanak announced the project today, Nov 18, noting that it will be backed by a US$183 million loan from the Asian Development Bank (ADB).
One of the main objectives, he explained, is to bring solar power generated in Krakor district, Pursat province, into the national grid for distribution across the country.
A solar power development with a combined generation capacity of more than 1,100 megawatts is currently under construction in Krakor district, which the minister described as one of the largest green energy projects in the Asean region.
The project is expected to help Cambodia achieve its target of generating at least 70 per cent of its electricity from clean energy sources by 2030. Currently, about 63 per cent of the country’s electricity comes from clean sources, including hydropower, solar power and biomass.
“The second objective of building this transmission line and substations is to strengthen the stability of our national grid. This means we are continuously developing the national grid to reduce power outages in economic zones, industrial areas, agricultural areas and residential communities in the future,” noted Rottanak.
He said strengthening the electricity network would improve people’s livelihoods and support investment by both domestic and foreign investors as the country’s demand for electricity increases.
The third objective is to stimulate economic growth and create new employment opportunities.
He cited Kampong Tralach district in Kampong Chhnang province as an example, saying more than 50,000 workers were currently employed in factories there.
“Expanding electricity supply to Kampong Tralach district under this project will enable factories and enterprises to grow further, potentially increasing the number of workers to more than 100,000 in the near future,” he said.
He added that creating jobs in local communities was part of the government’s efforts to provide employment opportunities for young people and reduce labour migration to areas far from their families.
The minister noted that electricity fed into the national grid would not only serve the three provinces directly connected by the project but also support the development of tourism, agriculture and industry in other provinces linked to the wider network.
The minister thanked local authorities and residents for their support and cooperation in facilitating the project’s implementation. He called on them to continue working together until construction is completed so the project can deliver benefits to local communities and the national economy. - The Phnom Penh Post/ANN