A smartphone with a displayed Micron logo is placed on a computer motherboard in this illustration taken March 6, 2023. REUTERS/Dado Ruvic/Illustration
(Reuters) -A new underground transmission line was approved by the New York State Public Service Commission linking an existing Clay substation with Micron Technology's proposed semiconductor megafab facility in Onondaga County, Governor Kathy Hochul announced on Thursday.
The two-mile, 345-kilovolt line is a key piece of infrastructure for Micron’s planned $100 billion investment in Central New York, the largest private investment in the state’s history, Hochul's press release said.