KOTA KINABALU: The components of the Emergency Restoration System (ERS) temporary tower arrived at the site of the collapsed transmission tower in Ranau on Friday (Nov 27) morning to restore the electricity supply line connecting Sabah’s West Coast and East Coast.
Sabah Electricity said the lorry transporting the ERS temporary tower container arrived safely at the site of transmission tower T313 at 1.07am.

"Sabah Electricity greatly appreciates your patience and sincerely regrets any inconvenience caused,” it said in a statement on Friday.
The company also apologised for the inconvenience experienced throughout the disruption period and expressed its appreciation for customers’ patience and cooperation.
It said Sabah Electricity’s technical teams had been mobilised to carry out preparatory work before the installation of the ERS tower begins, while prioritising safety and compliance with established work procedures.
Sabah Electricity is also stepping up all efforts to expedite the restoration of electricity supply to affected consumers following the collapse of transmission tower T313 in Ranau on Thursday (Nov 26).
The collapse of tower T313, detected at 6.04am on Thursday, severed two transmission line circuits supplying electricity from Sabah’s West Coast to its East Coast, disrupting electricity supply across eight districts and affecting 153,599 registered consumers.
Members of the public can follow the latest updates via Sabah Electricity’s official Facebook page, Sabah Electricity Careline, or contact the company through its hotline at 15444, 088-515000, or WhatsApp at 019-8525427.- Bernama