First package of Penang's Juru-Sungai Dua traffic dispersal project is 54.61% complete


By ANDY LO

GEORGE TOWN: The first package of the RM3bil Juru-Sungai Dua Traffic Dispersal Project (PTJSD) has achieved 54.61% physical progress as at Sunday (Nov 8), according to PLUS Malaysia Bhd.

In a statement on Tuesday (Nov 17), the highway concessionaire said this reflected positive progress in the implementation of the strategic infrastructure project.

"Package One comprises improvement works to the access ramps at the East-West Interchange Roundabout, as well as the construction of a new bridge along Jalan Tun Hussein Onn.

"These works aim to increase road capacity and improve traffic flow in the surrounding area," it said.

PLUS said the subsequent packages were also being planned in phases, with Packages 2 to 5 currently at the final tendering stage.

"Packages 2 and 5 involve construction works along the sections between Juru Toll Plaza and Juru Lay-by, as well as between Samagagah Lay-by and Sungai Dua Toll Plaza.

"Packages 3 and 4 comprise the construction of elevated sections and interchanges between Juru Lay-by and Samagagah Lay-by," it said.

The 17.4km project connects the Juru Toll Plaza and Sungai Dua Toll Plaza.

"Upon completion, the project is expected to enhance highway capacity, improve traffic flow and deliver long-term benefits to highway users and the surrounding communities," it added.

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

PBS eyeing at least five parliamentary seats under GRS
Only one name submitted for Negri Sembilan MB post, Palace to decide, says Ahmad Zahid
Negri Umno urges calm following MB's resignation
Fibre optic cables have no resale value, Fahmi warns would-be thieves
'I will not resign over Dewan Rakyat remark', says Ahmad Maslan
GOF seizes RM1.1mil in contraband cigarettes, tobacco in Tawau; local man arrested
E-hailing driver pleads not guilty to posting offensive TikTok content
Perak 2027 Budget to be tabled Nov 24, sign language interpretation introduced for first time
PAC flags 'unrepresentative' MediAsas pilot, zero hospital claims recorded
23 Pahang schools classified as dilapidated under Scale 7, Dewan Rakyat told

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read