Prasarana ramping up efforts to improve LRT reliability after challenging 2026


PETALING JAYA: Prasarana Malaysia Bhd is intensifying efforts to strengthen Light Rail Transit (LRT) service reliability through round-the-clock maintenance, closer engagement with suppliers and the introduction of 26 new train sets for the Kelana Jaya Line.

The measures form part of the rail operator's efforts to address technical challenges affecting train operations while improving service reliability and the passenger experience.

Prasarana acting president and group chief executive officer Dr Prodyut Dutt acknowledged that the Kelana Jaya Line had faced greater reliability challenges this year.

From January to August 2026, the Kelana Jaya Line recorded one incident for every 749km travelled, compared with one incident for every 1,066km during the same period in 2025.

"There is no denying the fact that we are having more incidents in 2026 than we had last year. On the Kelana Jaya Line, that represents a deterioration of about 30%," he told Bernama recently.

In contrast, the Ampang Line and Monorail recorded performance improvements of 20 and 80% respectively.

Dutt emphasised that prioritising the Kelana Jaya Line is crucial as it carries the highest volume of 290,000 daily passengers.

He revealed that 90% of disruptions on the Kelana Jaya Line stem from rolling stock issues, with two-thirds triggered by the automated emergency braking (EB) safety system.

The EB system automatically activates when onboard tachometer sensors, components that monitor the speed of a train's wheels, detect speed discrepancies above 5%. Cable wear and track vibrations can affect the sensors and contribute to these discrepancies.

Dutt said the issue was linked to the operating characteristics of the line's linear induction motor (LIM) system, which has been in service since 1998.

"The design characteristic of a LIM system is that the braking is naturally very hard. Overseas operators using the same system, such as in Vancouver, face the same issues with tachometers and emergency braking," he said.

However, Dutt clarified that converting or replacing the LIM system entirely is not feasible, as it would necessitate replacing the entire power supply, signalling, track work and civil infrastructure, requiring Prasarana to operate within the existing design parameters.

On fleet condition, he said the Kelana Jaya Line operates 74 trains across three generations, including 26 first-generation four-car train units that have been in service for over 17 years.

An assessment found that overhauling trains aged 15 years would cost almost 90% of the price of a new unit, prompting Prasarana to order 26 new train sets worth more than RM1bil from Chinese manufacturer CRRC Corporation Limited.

The first new trains are scheduled to arrive in March 2029, with two sets expected to be delivered each month thereafter.

While the new fleet will support long-term improvements, Dutt said Prasarana was also implementing interim measures and engineering interventions to enhance operational stability before the trains arrive.

"That is why we are aggressively implementing interim measures and engineering interventions to stabilise operations," he said.

Prasarana has also worked with CRRC to refine the braking profile of the new trains during the final design review, with the aim of ensuring smoother deceleration and improving passenger comfort.

To manage immediate strain, Prasarana has mobilised 24-hour maintenance operations across depots and specialised workshops to inspect, service and rectify train systems continuously.

During a recent visit to its facilities, Bernama was given a first-hand look at these round-the-clock operations, including intensive maintenance within the electrical, door system and main repair workshops.

However, Dutt said global supply chain bottlenecks remain a challenge, with critical components such as tachometers facing long lead times of eight to 12 months, prompting senior engineering teams to meet directly with suppliers to expedite orders.

"Cost is not the issue because the government has been very supportive through government guarantees and approved five-year funding programmes. Our main challenge is the lead time for spare parts," Dutt said.

He added that a major overhaul of the train bogies – the heavy undercarriage structures that house the wheels, suspension and braking systems – on the nine-year-old third-generation trains is scheduled to begin in June or July next year.

To minimise passenger impact during service disruptions, Prasarana is refining its contingency measures by implementing train turnbacks at selected locations to reduce congestion at key stations, isolating affected track sectors, running shuttle loops and deploying feeder buses.

Dutt also said passenger communication is being strengthened through direct one-way WhatsApp broadcast alerts for registered users, while the presence of Auxiliary Police, station officers and Prasarana Troopers is being increased at station platforms and concourses to better manage passenger flow. – Bernama

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

King grants audience to IGP
Zara Qairina's mother refused post-mortem despite being briefed, inquest told
Malaysia cautious on proposal to co-chair The Hague Group, says Mat Hasan
Over 11,800 public, school toilets upgraded since 2023
Shafie, Leiking returned unopposed as Warisan top leaders
High Court grants Perikatan leave to challenge Registrar of Societies suspension order
Anti-ticket scalping regulations to be introduced in six months, says Fuziah
Melaka polls: PAS-BN talks at final stage, says Annuar Musa
Parliament to hold Special Chambers debate on haze
Teacher claims trial to negligence charges over student's death

Others Also Read