Gemas-Mentakab railway upgrade completed at RM41.7mil cost


BAHAU: The government is committed to strengthening rail connectivity across the country, says Transport Minister Anthony Loke.

He said this at the rehabilitation and upgrading of the Gemas-Mentakab railway line (Package A) completion ceremony.

“Through infrastructure improvements such as this, the government is committed to strengthening the rail network as the backbone of the country’s transport system, while increasing the use of public transport, enhancing connectivity between regions and supporting more inclusive and sustainable economic growth,” he said in his speech at the KTM station here on Friday (July 24).

Loke said the Gemas-Mentakab project was originally awarded in February 2016 with an expected completion date of Feb 20, 2019. However, the original contractor failed to complete the works and its contract was subsequently terminated.

He said the government resumed the remaining works under the 12th Malaysia Plan through an open retender process managed by the Negri Sembilan Public Works Department.

The project was completed on June 19 at a total cost of RM41.7mil.

Loke also commended the Negri Sembilan Public Works Department and contractors, Asia Communication and Electronic Sdn Bhd (Asiakom), for completing the project.

He said the Gemas-Tumpat railway upgrading project comprised three packages: Package A from Gemas to Mentakab, Package B from Mentakab to Gua Musang, and Package C from Gua Musang to Tumpat.

“To date, Package A and Package B have been fully completed, while Package C remains under implementation,” he said.

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

EC to meet on Oct 7 to set dates for 16th Melaka state polls
Najib has ‘good chance’ of leaving prison on same day RM50mil fine is paid, says Shafee
Melaka polls: BN to reveal candidate list closer to Nomination Day
Sabah edu fund helped over 27,000 students since mid-2022, says CM
Turn R&D into solutions that meet real-world needs, says Chang
Negri royal row: Conference of Rulers notified of Tunku Nadzaruddin's succession, say Undang and disputed chiefs
Negri royal row: Stay out of state matters, Undang and disputed ruling chiefs tell PM, AGC
Najib cannot afford RM50mil house arrest fine due to frozen accounts, says lawyer
Negri royal row: Undang, disputed ruling chiefs reject exco removal, label move unconstitutional
Seven foreigners nabbed in raids on beauty centres

Others Also Read