RTS train set testing starts today at Wani Hana Depot


Photo: Bernama

JOHOR BAHRU: Train Set 02, the first train set for the Johor Bahru-Singapore Rapid Transit System (RTS) Link project, arrived at the Wadi Hana Depot yesterday and is scheduled to undergo multiple tests, including a decoupling exercise starting Sunday (Nov 16).

RTS Operations Pte Ltd (RTSO) chief executive officer Dr. Ahmad Marzuki Ariffin said this would be followed by static tests to ensure all systems were in proper working order prior to the three phases of dynamic testing.

He said the dynamic tests would run from the depot to Bukit Chagar Station and across the international border to Woodlands North Station in Singapore before heading back to the depot to assess operational performance in actual conditions.

"Through these three dynamic tests, the train will run at low speed, and testing will take place under actual operational conditions on the mainline,” he told Bernama.

He added that the main tests to be carried out would cover the signalling system, communication system, and train performance on actual tracks, ensuring all systems operated smoothly and safely.

Ahmad Marzuki said the testing and commissioning of all eight RTS train sets was expected to take six to seven months, after which the trains would be cleared for driverless operation.

"This is important to ensure that each of our trains can communicate with other systems, including the power and signalling systems,” he said.

He said passenger capacity tests would also be carried out starting next year to ensure smooth RTS operations and user comfort.

Meanwhile, RTSO chairman Datuk Khairil Anwar Ahmad said the RTS Link project was progressing smoothly, with overall progress having reached 65 per cent to date.

He said all work was carried out in accordance with established standards to ensure completion within the scheduled timeline. 

"We have many staff on-site, so safety is maintained at the highest standard to ensure all work is carried out and completed, while keeping safety a top priority,” he said.

He added that all operational planning was carried out meticulously to prepare for every eventuality, including unpredictable weather conditions.

Train Set 02 was transported on four low loader 112-wheeler trailers, travelling 541 kilometres from the CCRC Batu Gajah facility in Perak on Nov 12 before reaching the Wadi Hana Depot yesterday.

Once it begins operations, the four-kilometre RTS Link project, connecting Bukit Chagar in Johor Bahru and Woodlands North Station in Singapore, is expected to carry up to 10,000 passengers per hour in each direction. - Bernama 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
RTS Link , phase , test , Tren 02

Next In Nation

RM200,000 allocation announced for more solar-powered street lights along Kangkar Bahru-Yong Peng road
Timely aid for single mothers, cancer patients, dialysis patients in Ayer Hitam
Over 860,000 self-employed individuals contribute to Perkeso, art sector still lowest
Woman drowns after MPV plunges into Sungai Muar
Sultan of Selangor receives coffee table book published by Bernama
'Millionaire Man' hands out RM100 cash to Klebang Beach visitors
Motorcyclist killed, wife injured in crash with lorry near Ipoh
Two injured in NSE crash between lorry and bus with 10 passengers
List out today: Recruits must confirm by Dec 25 for PLKN 3.0 Series 1 2026
Malaysia to establish Ombudsman to strengthen public sector integrity

Others Also Read