Power supply fully restored to Mid Valley City, surrounding areas, says TNB


KUALA LUMPUR: The power supply disruption caused by the fire at the main intake substation at Mid Valley Megamall was fully restored at 12.30pm Wednesday (May 17), says Tenaga Nasional Bhd (TNB).

TNB chief grid officer Dev Anandan said TNB’s inspection found that the substation was tripped at 10.27 am, causing power cuts from 10.51am.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Father, son injured after fire guts double-storey house in Klang
Packed schedule for PM Anwar during 'White Marble City' visit
Thunderstorms and heavy rain to hit Sarawak, Sabah and Labuan
Impact of the Bersatu purge
Unwrapping the dumpling
Nuclear energy still under study
JPJ seizes 145 luxury vehicles
Beating the odds to become top scorers
MSC CEO claims trial over RM1mil bribe for squash centre tender
Data, AI to anchor 13MP framework, says Fadillah

Others Also Read