‘Ministry did not impose late charges over delivery of LCS 1’


PETALING JAYA: The Defence Ministry did not impose liquidated damages or late charges of RM116.54mil on the company that was supposed to deliver the littoral combat ship (LCS) 1, said the 2019 Auditor-General’s Report.

At the same time, the report found that progress payments made for the ship exceeded the actual work progress by 21.1%.

The report said the company was supposed to deliver the LCS 1 in April 2019, but as of Dec 31,2019, or 245 days later, it had yet to be delivered.

The report added that as of June 30 this year, although the scheduled delivery of the ship had exceeded 12 months, the ministry had not issued a letter to the company demanding late charge penalty but had merely issued a reminder to the company on the delay.

The RM9bil contract for the delivery of six ships was from October 2013 to October 2023.

The report said that according to the contract, the ships were to be delivered in stages from April 2019 to June 2023.

In response, the ministry said as of June 10 or 435 days after the delivery of the LCS 1, the late payment charges stood at RM217.5mil.

It said it had issued a notice of claim of RM180mil to the company because of a capping on the claim.

The ministry added that as of July 1, the status of the progress of the LCS 1 was 56.7% compared to the planned 85.7% – a delay of 29.1% or 31 months.

The report noted that as of Dec 31, progress payments of RM910mil or 63.8% of progress payments had been made, although it was only at 42.7%.

It also found that late payment charges of RM15.04mil were not imposed on the company that was to supply 24 Lightweight Multiple Launchers – New Generation (LML-NG) between June 2018 and September 2018.

The audit found that 20 of the 24 launchers were delivered between 28 and 171 days late.

The ministry said it would act on the matter after getting a response from its legal department.

The A-G report also said nine armoured personnel carriers (APC) purchased by the ministry did not meet the specifications of the United Nations as they were unarmed.

The APCs, which were used in a UN peace mission in Lebanon, were first purchased by the Malaysian government, with the UN to reimburse the government.

Since the vehicles are not equipped with the remote control weapons station, the government lost out on RM2.2mil in reimbursements.

The ministry said the APCs passed the Final Acceptance Test and could be used for the United Nations Interim Force in Lebanon, and that the non-specifications were only for the weapons systems.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Malaysians in Japan urged to remain vigilant after 7.1-magnitude earthquake
Flight MH370 families want 'facts' as China court hears appeal
Bangladesh seeks Malaysia’s help to address urgent LNG shortage, says PM
Negri polls: Analysts can analyse, but voters are those voting, says Aminuddin
Welder dies while repairing water tank in Parit
Teen found drowned after being swept away by current in Sungai Kampar
Negri polls: 91% turnout for early voting, says EC
Company gave RM1mil to Bersatu after securing RM141mil contract, court hears
Enforcement of amended rice act will not target paddy farmers, says Deputy Minister
Immigration nabs 50 illegal immigrants in Kulai

Others Also Read