2011 A-G's Report: Rail project delay costs Govt RM3.6bil more


DELAYS to the 329km Ipoh-Padang Besar electric double-track rail project has cost the Government an extra RM3.6bil in costs on top of its RM12.49bil contract value.

The project has been delayed by 669 days, incurring additional costs on, among others, land acquisition (RM698.17mil), compensation for squatters (RM37.64mil), consultant's fees (RM265.96mil) and electricity reconnection chargers (RM203.48mil).

The Auditor-General's Report said there were also additional costs on legal fees (RM1.38mil), processing fees for deferred payment plan (RM10.05mil) and Bank Pembangunan Malaysia Bhd's interest charges (RM2.4bil).

The report noted that the appointment of MMC Gamuda Joint Venture Sdn Bhd (MGJV) as the main contractor for the design and building of the project was “not done through competitive bidding”.

“The auditor feels the appointment of a contractor without going through competitive bidding will leave the Government with limited choice in making a comparison, evaluation and selection of qualified contractors,” the report said.

It also disclosed that RM1.06mil was paid to CIMB Investment Bank Bhd and Maybank Investment Bhd for financial advice on the deferred payment plan.

“The auditor could not determine whether the financial advisory fee was at competitive rates because the ministry did not invite other banks to bid,” it said.

Responding to the audit, the Transport Ministry said it would, in future projects, ensure that 50% of land acquisition was completed first before appointing the contractors.

It said that whether it was done through competitive bidding or direct appointment, the contract was decided by the Government.

“The ministry will abide by the Government's decision,” it added.

Related Stories: 2011 A-G's Report: Unisel running at a loss and not up to mark 2011 A-G's Report: Half of ITIS lying idle 2011 A-G's Report: Take PHC to task for not keeping things on track' 2011 A-G's Report: Cattle and goat semen imported - and then wasted 2011 A-G's Report: Delay over bridge in Kota Baru, cost to increase 2011 A-G's Report:: Better review for govt agencies 2011 A-G's Report: Customs man RM1.82mil equipment buy not necessary

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Gua Musang car crash leads to discovery of house-breaking tools
Anwar invites professionals from MCOBA to provide input on national development
Ipoh police seek public help to locate missing man
Tengku Ampuan of Pahang receives master's degree from IIUM
Scholars, leaders must guard against corruption of knowledge, says Sultan Nazrin
Floods: 842 people evacuated in three Sabah districts
STEM Fest 2026 opens doors for youth to explore science, technology and innovation, says exco rep
Free ECRL trial rides draw crowds at Negri edition of Yakin Madani
Education Ministry urged to clarify Year One entry policy for six-year-olds
Sarawak polls: Unopposed wins in Betong reflect confidence in GPS, says Layar incumbent

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read