2011 A-G's Report: Rail project delay costs Govt RM3.6bil more


DELAYS to the 329km Ipoh-Padang Besar electric double-track rail project has cost the Government an extra RM3.6bil in costs on top of its RM12.49bil contract value.

The project has been delayed by 669 days, incurring additional costs on, among others, land acquisition (RM698.17mil), compensation for squatters (RM37.64mil), consultant's fees (RM265.96mil) and electricity reconnection chargers (RM203.48mil).

Win a prize this Mother's Day by subscribing to our annual plan now! T&C applies.

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

INTERACTIVE: More than half of Malaysia’s children at risk of obesity
Families adopt healthy lifestyles to help their overweight kids
‘Canting’ a love for batik
Ewaste discovered at Westport
KKB polls: Drama wakes up sleepy town
Look into TVET to prepare country for industrial boom
Tengku Hassanal’s expedition pays tribute to Sungai Pahang’s historical legacy
More FDIs set to flow in
Uncovering secrets of 5,700-year-old Penang Woman
Justice for Bella remains

Others Also Read