THREE flood walls, two flap gates and six mobile pumps, for about RM750,000.
The real fix -- a RM40mil project at Sungai Rasah in Shah Alam -- is targeted for 2031, or 2029 if the tender is split.
Put those figures next to one more.
The Drainage and Irrigation Department has about RM3.35bil in this year’s federal budget. That is roughly RM9mil a day.
So the three immediate measures cost about two hours of the department’s budget.
The long-term fix costs less than five days of it. And the capital of Selangor is told to wait five years.
Money is clearly not the problem. Time is.
According to the same announcement, the Sungai Rasah project is still at the preliminary design stage, with construction to start in 2028.
That is the part I find hard to accept.
Shah Alam suffered its worst floods in December 2021.
Five years later, the main project for one of its flood-prone basins has not finished its design.
I used to do this work. I was a design engineer on drainage and flood mitigation schemes in West Sussex, England.
The whole idea of the profession is in its name.
It is called flood mitigation, not flood reaction.
Mitigation is what you do before the water arrives.
Design and studies do take time, and they should not be rushed.
But they should be done before the flood, so that when the money is approved, the project is ready to build.
Old books, missing studies
The department’s web page of hydrology procedures − the basic methods engineers use to estimate rainfall and flood flows − lists 27 documents.
Twenty-four are dated between 1973 and 1983.
Some have been revised since, but the page, last updated in 2017, does not say so.
The national stormwater manual that drainage designs are checked against, was last issued in 2012.
A new edition has been in the department’s own plans since at least 2021. There is still no date for its release.
In 2021, the department commissioned a flood master plan study for the whole Sungai Klang basin, at about RM2mil.
It was due in late 2023. I have not been able to find it.
A flood hazard map for Selangor was presented to the state government in August last year.
The public can see flood hotspots online, but not the full map.
So we have a reference page that still shows 1970s dates, a manual from 2012, a study that has not been published and a map the public cannot fully see.
Walls and pumps are a mop. They clean up the water. They do not turn off the tap.
Three requests
Split the tender now and commit publicly to 2029, with a progress update every six months.
Publish the Klang river basin study and the Selangor flood hazard map, so that residents can see the risk and what is planned for their areas.
Give a date for the new stormwater manual and update the public reference pages.
We are not short of money. We are short of urgency.
Shah Alam residents will face several more monsoons before 2031, and they will be counting each one.
RAJA AHMAD FAUZAN