Tribunal orders electrician to refund RM3,500 for incomplete wiring job


Chandrasegaran says the electrician only came to his house once but has asked for additional funds to buy materials.

AN electrician has been ordered by Johor Consumer Claims Tribunal to refund a client RM3,500 in three tranches for failing to finish a job.

Tribunal president Lee Chim Thim ordered the respondent to pay the first tranche of RM1,500 to claimant N. Chandrasegaran on Nov 15, 2026, followed by the second (RM1,500) on Dec 15.

“The last payment of RM500 must be settled on Jan 15, 2027.”

Lee chided the respondent for not settling the amount earlier instead of waiting for the case to be brought to the Tribunal.

The respondent said he was having financial problems and worked as a p-hailing driver.

When met outside the Tribunal, Chandrasegaran said he hired the electrician from Taman Selatan, Kulai, on the recommendation of a friend.

The job scope included wiring his kitchen, two bathrooms, living area and car porch at his house in Taman Setia Eco Gardens in Gelang Patah, Johor.

“The total cost was RM6,000 and I paid RM3,500 via online banking in February this year,” said the claimant who works as a boilerman at an oleo-chemical plant in Pasir Gudang.

He said the electrician came to his house in February and hacked the kitchen walls but never came back.

In March, however, he was contacted by the respondent asking for RM500 to buy wiring materials.

“So I transferred RM500 to him,” said Chandrasegaran.

“When I asked why he only came once, he said he was busy with other jobs.”

Despite receiving RM4,000 in total, the respondent never finished the job.

“I had to fork out RM4,000 in April to hire another electrician from Gelang Patah who managed to finish the job in three weeks,” Chandrasegaran added.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Metro News

Solution to U-turn congestion in sight
Cops, varsity spearhead campaign to speak up and prevent bullying
Of temple gatherings and divine blessings
Young dance troupe scores hat-trick
Selangor trials electric compactor lorries for potential savings
Penang set for drone industry hub
Groups call for humane stray management in Perak
New Buddhist temple site approved in Kluang
Bigger water pumps for Johor Baru
Stamp of approval for local beadwork heritage

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read