KUALA LUMPUR: Aneka Jaringan Holdings Bhd
has secured a subcontract worth RM82.8mil for bored piling and reverse circulation drilling (RCD) works for the New Pantai Highway Extension Project.
In a filing with Bursa Malaysia, the group said its wholly owned subsidiary, Aneka Jaringan Sdn Bhd, had received and accepted a letter of acceptance from IJM Construction Sdn Bhd to undertake the works for Package 1 (Section 1 and 2A) of the project.
The subcontract involves bored piling works and RCD works, with the project commencing on March 2, 2026.
Aneka said bored piling works for Sectional Completion 1 are scheduled to be completed within 18 months from the date of possession of the site, while Sectional Completion 2 involving Ramp D (Pier D3 to D8) is to be completed within three months from the same date.
The RCD works are expected to be completed within 20 months from the date of possession of site.
Aneka expects the project to contribute positively to its consolidated earnings and net assets for the financial years ending Aug 31, 2026, 2027 and 2028.