The country’s Cabinet agreed new rules on noise and water use for data centres after a review sparked by public concern over an AI-driven construction boom.
“The use of national resources must not adversely affect the public,” Finance Minister Ekniti Nitithanprapas told a news conference yesterday.
The government said in September it would tighten oversight of data centres, asking developers of nearly 50 under-construction projects to pause work until new rules were drawn up.
Proposed standards include limiting noise at site boundaries to 70 A-weighted decibels (dBA), according to a government data centre board.
That is slightly quieter than a vacuum cleaner, according to a comparison chart published by Yale University.
The government also proposed capping nearby temperature increases to 1-2˚C, and said cooling water must be recirculated and tested before discharge. New zoning rules were also approved in principle, with centres consuming more than 20 megawatts of energy set to be located in industrial zones and face stricter oversight.
Ekniti said the government also received a large number of speculative applications.
More than 110 applicants had requested over 30,000 megawatts of electricity, he said, but only about a quarter or fewer had genuine investment plans.
Eligible projects approved before August 14 will have one year to meet environmental guidelines. — AFP