Anthropic's Australian data centre overwhelmingly opposed by residents


An Anthropic, PBC (ANT) sign at One Times Square on the day Anthropic holds their initial public offering (IPO) at the NASDAQ Market site in New York City, US, November 19, 2026. REUTERS/Shannon Stapleton

SYDNEY, Nov 20 (Reuters) - A data centre ⁠planned in regional Australia with Anthropic as its anchor tenant is overwhelmingly opposed ⁠by residents, a filing for the project showed, setting the scene for a ‌showdown between the AI company and thecommunity hosting its first Australian facility.

Of nearly 600 public submissions on the proposed Western Downs Digital Park, about 250 km (155 miles) west of Brisbane, two expressed support for the project and one ​was neutral, according to the filing. The remaining 595 opposed ⁠it or asked for a delay ⁠until developers cleared certain environmental hurdles, the filing said.

"A significant number of submissions raise reasonable matters ⁠regarding ‌water, power, noise, roads, housing and the scale of the project," the filing, lodged on behalf of developer Zerra DC, said.

Representatives of Zerra and Anthropic were not immediately ⁠available for comment.

The initial response, though far from binding, gives ​a sense of the souring ‌relationship between communities and the so-called AI factories being built at pace around the ⁠world in a ​boom McKinsey has valued at $7 trillion by 2030.

Already in Australia, Goodman Groupscrapped a roughly A$1.2 billion data centre planned for Sydney in September after a public backlash, whileNextDC delayed a project in Melbourne amid ⁠resident concerns about energy use, triggering a shares selldown.

The ​Anthropic project is on farmland and further from the suburbs, but with a planned computing load of 1.44 gigawatts would be one of the country's biggest. About one-third of the submissions were from ⁠people who lived within 200 km of the site, the filing said.

Objectors mostly cited concerns about water use, electricity demand and prices, noise, road damage from construction traffic and pressure on housing.

Before the data centre project named Anthropic as its tenant on September 15, it had received ​five objections in a month, a log of public comments showed, ⁠with the rest arriving between then and November 11, when the local government stopped accepting submissions.

The ​filing about Australian data centre submissions was published the ‌same week Anthropic made its stock market debut on ​Wall St, pricing its initial public offering on November 18 in a deal that valued the company at around $1.5 trillion.

(Reporting by Byron Kaye; Editing by Stephen Coates)

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read