NYSE parent ICE launches tool to assess data-center construction delays


FILE PHOTO: Chillers that cool water are connected to a data center building during a tour of the OpenAI data center in Abilene, Texas, U.S., September 23, 2025. REUTERS/Shelby Tauber/Pool/File Photo

Nov 17 (Reuters) - Intercontinental ⁠Exchange launched a tool on Tuesday that ⁠estimates the risk of US data-center ‌projects being delayed or halted, as community opposition and political scrutiny threaten the rapid expansion of infrastructure needed for ​AI.

Here are more details:

• The ⁠tool evaluates permitting records, ⁠electricity and water costs, as well as local ⁠economic ‌conditions and mortgage-market data across more than 3,100 US counties

• The NYSE ⁠parent said its disruption model, trained on ​thousands of ‌permitting and project outcomes, achieved 77% accuracy

• ⁠The launch ​follows US midterm elections in which Democrats gained control of both chambers of Congress, potentially strengthening ⁠efforts to curb data-center expansion ​over concerns about power consumption, water usage and pollution

• Democratic lawmakers, including Alexandria Ocasio-Cortez, have proposed ⁠pausing new data-center construction and expansions until Congress adopts safeguards covering utility costs, environmental damage and community oversight

• "Data center capital is moving faster ​than local permitting and community ⁠consensus and that gap is now a ​material financial risk," said Larry ‌Lawrence, head of the Geospatial ​Intelligence team at ICE

(Reporting by Pragyan Kalita in Bengaluru; Editing by Shreya Biswas)

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read