Nvidia, Broadcom shielded as AI power crunch hits chip supply chain, says Morgan Stanley


An NVIDIA logo and a computer motherboard appear in this illustration taken August 25, 2025. REUTERS/Dado Ruvic/Illustration

Oct 5 (Reuters) - Nvidia ⁠and Broadcom are relatively insulated from a worsening ⁠US data-center power crunch, but any resultant delay ‌in AI deployments can affect makers of memory, optical and other secondary chip components, Morgan Stanley said on Monday.

• The brokerage ​estimated last month that US data-center ⁠developers face a 34% ⁠net power shortfall through 2028, equivalent to 32 GW, after ⁠accounting ‌for measures such as behind-the-meter generation and fuel cells

• The AI boom has triggered ⁠billions of dollars in data-center investment, but the ​vast computing ‌and electricity needs of generative AI are increasingly ⁠running up ​against US power supply issues

• Morgan Stanley and Goldman Sachs have both flagged mounting constraints on the US data-center ⁠buildout; GS expects limited near-term impact ​from political pushback, while MS sees labor, power and political challenges

• Morgan Stanley said it does not see the ⁠bottlenecks putting Nvidia or Broadcom's 2027 forecasts at risk, citing their visibility into chip placement, geographic expansion and coordination between data centers, semiconductor suppliers and the ​power supply chain

• If chip capacity ⁠cannot be deployed, customers could push out deliveries or ​cancel orders, with memory, optics, ‌power-management and analog components most exposed ​to inventory disruption, the brokerage said

(Reporting by Kanishka Ajmera in Bengaluru; Editing by Joyjeet Das)