Nvidia's biggest customers delaying orders of latest AI racks, The Information reports


FILE PHOTO: A smartphone with a displayed Nvidia logo is placed on a computer motherboard in this illustration taken March 6, 2023. REUTERS/Dado Ruvic/File Photo

(Reuters) -Nvidia's top customers are delaying orders of the AI chip leader's latest 'Blackwell' racks due to overheating issues, the Information reported on Monday.

The Santa Clara, California-based company's shares fell more than 4% in early trading.

The U.S. government also said earlier in the day it would further restrict AI chip and technology exports, potentially hurting Nvidia's sales.

The first shipments of racks with Blackwell chips have been overheating and exhibiting glitches in the way chips connect to one another, the Information reported.

A rack, used in data centers, is a structure that houses chips, cables and other essential equipment.

Major customers Microsoft, Amazon.com's cloud unit, Alphabet's Google, and Meta Platforms have cut some orders of Nvidia's Blackwell GB200 racks, according to the report.

Nvidia and Amazon declined to comment, while Microsoft, Google and Meta did not immediately respond to Reuters requests for comment.

The so-called hyperscalers had each placed Blackwell rack orders worth $10 billion or more, the report said.

Some of the customers are waiting to snag a later version of the racks or plan to purchase the company's older AI chips, according to the report.

Microsoft was initially planning to install GB200 racks with at least 50,000 Blackwell chips in one of its Phoenix facilities, the report added.

However, key partner OpenAI asked Microsoft to provide it with an older generation of Nvidia's 'Hopper' chips as delays popped up, the report said.

It is unclear how the order cuts would impact Nvidia's sales as there may be other buyers for the "glitchy" GB200 server racks, the report said.

The company is on track to exceed an earlier target of recording several billion dollars in revenue from Blackwell chips in its fourth fiscal quarter, CEO Jensen Huang said in November.

Huang had also denied earlier media reports of a flagship liquid-cooled server containing 72 of the new chips experiencing overheating issues during initial testing.

(Reporting by Arsheeya Bajwa in Bengaluru; Editing by Shreya Biswas)

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Tech News

Mobile phone-owning 13 to 16-year-olds increasingly targeted by scams
AI helps some workers but hinders those with skill, know-how – study
TikTok to give package kits on its website for US Android users to download app
Human artists could disappear if copyright not protected from AI
Start your own blog for more space and freedom to share your material
Meta prepares for layoffs on Monday -internal memo
Coinbase must face customer lawsuit in New York
Iliad to invest $3.1 billion to boost AI infrastructure in Europe
OpenAI's Altman envisions Stargate-like programme for Europe
Motorola refused permission to appeal UK emergency services network case

Others Also Read