US power, tech companies lament snags in meeting AI energy needs


FILE PHOTO: Figurines with computers and smartphones are seen in front of the words "Artificial Intelligence AI" in this illustration taken, February 19, 2024. REUTERS/Dado Ruvic/Illustration/File Photo

NEW YORK (Reuters) - U.S. electrical systems are not expanding fast enough to meet rapidly growing power needs of technology like Generative AI, prompting data center businesses to sometimes bypass utilities, executives said at an energy conference this week.

Layers of regulations, citing and permitting processes, and frequent legal fights brought by environmental and community groups, have slowed new power projects from connecting to the grid, and posed a threat to profits by traditional power companies like regulated electric utilities.

"Regulation and permitting within the United States is abysmal," Brad Stansberry, who leads the financial management practice for the power and utility industry at services firm KPMG, said at the AI: Powering the New Energy Era summit in Washington on Wednesday.

The delays have led data center businesses to bypass utilities and strike deals directly with power generators or build their own supply.

Data center developer Aligned, which is one of the biggest companies of its kind with 2.5 gigawatts of capacity, is hastily pursuing power supplies after spending several years focusing on buying land for its operations.

"We always assumed there would be power, but obviously that assumption was woefully inaccurate, so now we're chasing where power is," said Phill Lawson-Shanks, Chief Innovation Officer at Aligned.

Among its considerations for electricity, Aligned is looking at using small modular reactors, or a type nuclear energy system that is currently in development in the United States, to power some of its projects, and is working with utilities on projects when possible, Lawson-Shanks said. "Where we can't, we will have to have them behind the meter," he added.

Power companies also lamented the constraints with meeting the electricity needs of companies supporting chatbots like ChatGPT, which requires about 10 times the energy as a Google search, and other forms of artificial intelligence.

"It's difficult to get anything built quickly," said Michael Keyser, who heads National Renewables Cooperative Organization, which represents about two dozen generation and transmission cooperatives, along with distribution cooperatives. "So I think it's a natural outcome of that for why you see data centers and tech companies pursuing their own power purchasing now."

Regulated power utilities cited slow regulatory process to expand their systems, particularly with the demand for renewable energy such as solar and wind, while also hoping the surge of demand by big technology would help their companies grow.

"If you're driving that bus, it's actually going to be easier for us," said Brian Bird, chief of electric utility and natural gas company NorthWestern Energy, referring to technology companies taking the lead in power generation.

(Reporting by Laila Kearney; Editing by Liz Hampton and Josie Kao)

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

   

Next In Tech News

Abu Dhabi AI company Presight takes majority stake in tech venture AIQ
Anthropic releases business chatbot in hunt for corporate dollars
US prosecutors examining financial transactions at Block, NBC News reports
Roblox players to start seeing video ads in its virtual realms
Garmin's Q1 results beat on strong demand for fitness, auto products
AMD, Super Micro spark chip selloff as earnings miss lofty AI expectations
OnlyFans faces UK investigation into age-verification measures
Amazon’s Twitch starts rival to TikTok in short-form video
Google and Apple now threatened by the US antitrust laws that helped build their technology empires
Crypto washout sends bitcoin below $58,000 ahead of Fed decision

Others Also Read