KOTA KINABALU: The Sabah government should consider financing the RM1.4bil Southern Link Phase 1B project instead of waiting for federal approval, Kota Belud MP Isnaraissah Munirah Majilis says.
She said recurring power disruptions have highlighted the urgent need for stronger electricity infrastructure, requiring the state to take proactive action.
In a statement on Sunday (Nov 29), she said Sabah should consider adopting an approach similar to Sarawak's, where the state government advanced funding for a federal project to accelerate implementation.
Isnaraissah made the proposal following the collapse of transmission tower T313 in Ranau on Thursday, which disrupted electricity supply to 153,599 registered consumers across eight districts on Sabah's east coast.
While welcoming calls by Domestic Trade and Cost of Living Minister Datuk Armizan Mohd Ali for the federal government to immediately approve Southern Link Phase 1B, she said the state government has the authority and financial capacity to begin moving the project forward.
She noted that regulatory powers over electricity supply were devolved to Sabah in January 2024 and the state government has repeatedly stated that Sabah's financial reserves stand at RM8.6bil.
"The cost of Phase 1B is about RM1.4bil, equivalent to roughly 16% of the state's reserves, and can be financed in stages," she said.
She proposed Sabah would advance funding for the project over a three-year period to allow construction to proceed concurrently with Phase 1A, which is expected to be completed by September 2028.
However, she said that any state funding should be backed by a written agreement requiring the federal government to reimburse Sabah, similar to the arrangement used for the Sarawak Cancer Centre project.
She proposed that if repayment is not made within the agreed timeframe, the state's contribution value should be converted into an equity stake for the Sabah government in Sabah Electricity.
Isnaraissah also called for the state government to use its authority over land matters to expedite land acquisition and approvals along the proposed Upper Padas-Tawau route, which forms the approximately 270km Phase 1B component of the Southern Link project.
She said stable electricity and water supplies should be a priority over other spending priorities, including plans to establish a Sabah sovereign wealth fund.
"Stable water and electricity supply are basics for people's well-being and the state's economic growth. The government should prioritise critical infrastructure to prevent east coast residents from having to endure repeated supply disruptions," she said.
Phase 1B of the Southern Link project remains under consideration under the 13th Malaysia Plan, while Phase 1A, involving a 60km transmission line, is currently under implementation.