KOTA KINABALU: The main structure of the temporary Emergency Restoration System (ERS) tower has been erected at Tower T313 in Ranau as Sabah Electricity races to restore a critical power transmission line between the east and west coasts.
In a progress update on its Facebook page, the utility company said its technical team had completed the installation of the main temporary tower structure at 1.45pm on Saturday (Nov 28).
Sabah Electricity said the team would now focus on installing the tower's crossarms and supporting components in preparation for the next phase, involving the installation of transmission cables.
The ERS tower serves as a temporary solution to restore transmission capabilities while longer-term repairs and reconstruction works are carried out.
Sabah Electricity described the progress as an important development in the ongoing effort to recover the electricity transmission corridor linking the state's east and west coast regions, a key component of Sabah's power network.
Sabah’s east coast was hit by a blackout on Nov 24 after a transmission tower collapsed in Ranau. The incident affected 153,599 registered consumers.
Full supply restoration is targeted by Dec 3 at the latest.
Sabah Electricity said safety continues to be prioritised throughout the restoration process in its efforts to expedite the work and restore electricity supply stability as quickly as possible.
It also thanked consumers for their patience, support and understanding as restoration works continue.