KUALA UMPUR: The Public Accounts Committee (PAC) will summon key witnesses from the Works Ministry and Sabah Public Works Department (JKR) on Nov 25 to testify in its investigation into the management and implementation of the Sabah Pan Borneo Highway Phase 1 project.
PAC chairman Datuk Mas Ermieyati Samsudin said the initial proceedings follow a meeting with five Sabah MPs on Wednesday (Nov 18).
The meeting with the MPs was held to obtain first-hand accounts of the project's progress and problems on the ground.
Among the issues highlighted by the MPs were construction site conditions, daily difficulties faced by residents, as well as risks to road users caused by prolonged project delays.
"The actual situation on the ground has given us a clearer understanding of the causes of the problems, helping PAC conduct a more focused investigation before official witnesses are called," she said at a press conference in Parliament on Thursday (Nov 19).
The five MPs were selected as the project route runs through their constituencies, and there have been issues with physical progress of the construction, including sections classified as sick or delayed projects.
The MPs are Datuk Dr Mohammad Yusof Apdal (Lahad Datu), Datuk Seri Dr Ronald Kiandee (Beluran), Datuk Seri Wilfred Madius Tangau (Tuaran), Datuk Siti Aminah Aching (Beaufort) and Isnaraissah Munirah Majilis (Kota Belud).
Mas Ermieyati said PAC would also summon parties involved in the project's management and implementation, including officers and individuals who had served since the project was first planned.
"For the first time, PAC has also invited the Sabah Public Accounts Committee to participate in the proceedings throughout the investigation," she said.
She stressed that PAC would not compromise on any breaches of financial procedures or abuse of power, and would ensure that those responsible were held accountable.
She added that the PAC would seek the Malaysian Anti-Corruption Commission (MACC)'s full cooperation in examining the facts and evidence presented, and refer any findings of misconduct for further enforcement action.
The investigation follows findings in the Auditor-General's Report Series 2/2026 on the management of the project.