Poor contractor management behind 77% of JKR's sick projects


KUALA LUMPUR: Weak contractor management is the reason behind 77% of the 33 sick projects under the Public Works Department (JKR) as of Sept 30, says Datuk Seri Dr Ahmad Maslan.

The Deputy Works Minister said problems mainly involve ineffective planning and coordination of work on site, insufficient manpower and weaknesses in managing machinery and the supply of building materials.

The 33 sick projects make up 3.77% of 875 projects under construction and supervised by JKR, with a combined contract value of RM40.7bil.

"Based on an analysis of the 33 sick projects, 77% were caused by weaknesses in contractor management," he said during Question Time in the Dewan Rakyat on Wednesday (Oct 7).

He said the number of sick projects had reduced to 45 through close monitoring and continuous recovery action by JKR and contractors.

He was replying to Datuk Mohd Suhaimi Abdullah (PN-Langkawi), who asked whether the ministry planned to tighten contractor selection and performance evaluation, given that most sick projects were linked to contractors' management and financial problems.

The ministry and JKR have also set up a Sick Project Monitoring Committee, which meets monthly to track progress and coordinate mitigation measures with other public agencies, local authorities and utility providers and its members also carry out site visits.

Ahmad said the Finance Ministry had agreed to two other changes to tender requirements.

Certified true copies of companies' financial statements can now be endorsed by individual chartered auditors, not only audit firms, following engagement with the Association of Malay Chartered Accountant Firms of Malaysia.

Bidders for JKR projects registered in the department's Skala system are also exempt from submitting forms declaring their current work in hand and current work performance, which existing rules require with every tender.

In February 2025, the ministry said 29 of 801 projects under JKR supervision were classified as sick as of January 2025.

 

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Melaka polls: PN first-timer buoyed by grassroots response in Bukit Katil
Anwar urges construction workforce to acquire robotics, automation and digital skills
Ramkarpal: Najib may have to serve 1MDB sentence at Kajang Prison if SRC jail term deemed completed
M'sia must develop, export own construction tech, says PM
AGC files bid to review Najib’s discharge order
KKB water surge incident: Five found dead, three still missing
Malaysia targets 500,000 affordable homes by 2030, says Anwar
S'wak to adopt hybrid financing model in transition to green economy, says Abang Jo
Melaka polls: Safeguards tightened after alleged cyberattack on EC website, says Ramlan
Seven nabbed over RM28.4mil jewellery heist at Johor pawnshop

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read