Cross-border RTS Link construction on track at 65% completion


JOHOR BARU: Construction of the Rapid Transit System Link (RTS Link) connecting Johor and Singapore is progressing smoothly, with the project reaching about 65% overall completion, according to its operator.

The information was shared with the media during Transport Minister Anthony Loke’s visit to the Bukit Chagar station construction site on Monday (Nov 3).

He said the RTS Link has three key components - the rail depot, the Bukit Chagar station and the Immigration, Customs and Quarantine (ICQ) complex - each showing strong progress.

“The link’s depot has reached 91% completion, the Bukit Chagar station is at 73%, while the ICQ complex has achieved 76.8%,” he told reporters after a briefing on the project.

Loke, who also toured each level of the building, said the structural works for the station and ICQ building have been completed, with work now advancing to system installation and passenger facilities.

“Passengers boarding from Bukit Chagar will move through multiple levels, ticketing on level one, Malaysian immigration and customs checks on level two, followed by Singapore immigration clearances on level three before reaching the boarding platform at the same level,” he said.

He added that track installation has also been completed and that the first RTS Link trains are expected to arrive at the Wadi Hana depot in the middle of this month.

Despite the technical complexity and cross-border coordination required, Loke said the project remains on schedule for completion by Dec 31, 2026, ahead of the January 2027 launch.

“There are many challenges, but mitigation measures are in place. We have 14 critical months ahead and I will monitor this closely, including visiting every three months,” he said.

Meanwhile, RTS Link operator, RTS Operations Pte Ltd chief executive officer Dr Ahmad Marzuki Ariffin said system works and operational preparations are about 65% completed.

“Our next milestone, as mentioned by the minister, is the arrival of the trains in Johor this month,” he said, adding that the link will operate with eight four-car train sets when fully commissioned.

He also said trial runs are expected to begin in July next year, once all integration tests are completed.

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Thunderstorms and rain to hit 10 states, KL, Putrajaya and Labuan
Strong winds complicate efforts to put out 51.4ha Punggai peat fire
Five men arrested, RM3,200 worth of ketum seized in separate raids in Perak
KL police announce major road closures and drone ban ahead of 69th National Day
Negri cops nab suspect believed to have burnt several copies of the Quran
Green turtles return to Kelantan coast after three decades
Different audit methods behind RM4.8bil TH gap, says former auditor-general
Marine cops seize nearly RM500,000 worth of illicit ciggies in Tawau
PAC should prioritise investigating TH's post-2017 affairs, says Zahid
Amirudin tasked with detailing cooperation for Melaka state election

Others Also Read